Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (September 8 – September 12):
- Madison has been milled from 37th Street to Seven Lakes Drive.
- Median cover material has been completed.
- Waterline updates are continuing north on Madison Avenue.
- Sidewalk continues to be poured around the roundabout.
- Final grading continues for stabilization.
Looking ahead:
- Top lift of asphalt on the west, north, and east legs of the roundabout
- Roadway grading along the milled section on Madison Avenue
- Waterline updates will continue north on Madison Avenue.
- Sidewalk will continue to be poured around the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Dr.
Please refer to the photos below for a visual update of progress.
Light poles are installed around the roundabout.
Cassions are installed at the southwest corner of the roundabout.
Share Weekly project updates 9/1/2025 - 9/5/2025 on Facebook
Share Weekly project updates 9/1/2025 - 9/5/2025 on Linkedin
Email Weekly project updates 9/1/2025 - 9/5/2025 link
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (September 8 – September 12):
- Madison has been milled from 37th Street to Seven Lakes Drive
- Median cover material has been completed.
- Waterline updates are continuing northward.
- Sidewalk continues to be poured around the roundabout.
- Final grading continues for stabilization.
Looking ahead:
- Top lift of asphalt on the west, north, and east fingers of the roundabout
- Roadway grading along the milled section on Madison Avenue
- Waterline updates will continue north on Madison Avenue.
- Sidewalk will continue to be poured around the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Dr.
Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
Share Weekly project updates 8/25/2025 - 8/29/2025 on Facebook
Share Weekly project updates 8/25/2025 - 8/29/2025 on Linkedin
Email Weekly project updates 8/25/2025 - 8/29/2025 link
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (August 25 – August 29):
- Median cover material has continued.
- Waterline updates continue along the project.
- The truck apron has been completed.
- The concrete pavement for the roundabout has been poured.
- Grading continues for sidewalk sections.
- Sleeper slabs have been poured for the roundabout.
- Asphalt has begun being paved around the roundabout.
Looking ahead:
- Median cover material will be finished.
- Waterline updates will continue northward from Hem Fir.
- Sidewalk will continue to be poured around the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Drive.
Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
Share Weekly project updates 8/18/2025 - 8/25/2025 on Facebook
Share Weekly project updates 8/18/2025 - 8/25/2025 on Linkedin
Email Weekly project updates 8/18/2025 - 8/25/2025 link
Hello, Loveland!
Here’s last week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (August 18 – August 25):
- The median cover material is now being poured.
- The waterline updates are continuing northward of Hem Fir.
- The construction of the sidewalk continues to be poured around the roundabout.
- Grading continues for sidewalk sections.
Looking ahead:
- The median cover material will continue to be poured.
- The concrete truck apron will be poured in the roundabout.
- Waterline updates will continue northward from Hem Fir.
- Sidewalk construction will continue around the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Drive.
Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link)(External link)(External link)(External link)(External link). Thank you for your patience as we complete these improvements!
Share Weekly project updates 8/11/2025 - 8/15/2025 on Facebook
Share Weekly project updates 8/11/2025 - 8/15/2025 on Linkedin
Email Weekly project updates 8/11/2025 - 8/15/2025 link
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week:
- Curb and gutter was poured in the roundabout.
- Waterline installation and testing are being finalized.
- Sidewalk is beginning to be poured around the roundabout.
- Grading continues for sidewalk sections.
- Roundabout medians are being prepped for median cover material.
Looking ahead:
- Median cover material will start pouring.
- Waterline updates will continue northward from Hem Fir.
- Sidewalk will continue to be poured around the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Drive.
Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link)(External link)(External link)(External link). Thank you for your patience as we complete these improvements!
Share Weekly project updates 8/4/2025 – 8/8/2025 on Facebook
Share Weekly project updates 8/4/2025 – 8/8/2025 on Linkedin
Email Weekly project updates 8/4/2025 – 8/8/2025 link
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (August 11 – August 15):
- Finished installing road base in the roundabout.
- Poured curb & gutter on the outside edges of the roundabout.
- Set stringline for more curb & gutter (median islands) in the roundabout.
- Removed part of the old Madison roadway and installed 350-ft of new waterline.
Looking ahead:
- Pour curb & gutter in the roundabout.
- Finish waterline installation and testing near Hem Fir. Notifications about water shutoffs will be communicated to affected residents by Loveland Utilities.
- Start removals of existing signs south of the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Dr.
Please refer to the photos below for a visual update of progress.


Share Madison Avenue Construction Update – July Recap on Facebook
Share Madison Avenue Construction Update – July Recap on Linkedin
Email Madison Avenue Construction Update – July Recap link
The Madison Avenue Corridor Improvement Project officially began on July 7, and significant progress has already been made. In this update, you’ll find a summary of what’s been accomplished in July — and a look ahead at what’s coming next.
Week of July 7–11:
- Mobilization began with the removal of pavement, curbs, islands, signage, and topsoil at the new roundabout location at Madison Avenue and 37th Street. Erosion control was installed around the work area.
- Initial grading work was underway; essential to establish accurate elevations and a stable foundation for the roundabout and approaches.
- Preparations for subsurface utility infrastructure installations were initiated

Week of July 14–18:
- Power and fiber optic utilities were relocated within the roundabout and continued south along Madison Avenue.
- Grading continued despite mid week rain delays; however, considerate progress was push forward with the roundabout and approaches starting to take visible shape.
- Storm sewer and irrigation pipe installation began, advancing underground infrastructure work.

Week of July 21–25:
- Grading work continues for the new roundabout, with crews addressing soft spots caused by rain. As a result, some planned activities have been delayed by a few days.
- Storm sewer and irrigation pipe installation in the roundabout area is now complete, and tree removals have begun throughout the entire project area.

A look ahead:
- Utility relocations will continue south of the roundabout toward 29th Street.
- Traffic communications conduits will be installed within the roundabout area.
- Crews will begin placing a new road base in preparation for concrete curb and gutter installation.
- Pavement removal on Madison Avenue, between 29th Street and Seven Lakes Drive, is in progress. Removal of asphalt will only occur to address waterline tie-ins. The project team will maintain access for all adjacent property owners while this work is being done.

Traffic and Detours:
Madison Avenue remains close between 29th and 37th Streets and 37th Street is close between Monroe Avenue and Seven Lakes Drive. As school begins, commuters should plan their routes ahead.
Local access to Madison Avenue is only available for those who live or own property along Madison Avenue between 29th and 37th Streets. Commuters outside the construction limits should follow the designated detour routes by using the following streets:
- North Boise Avenue
- Monroe Avenue
- 29th Street
- US 34
For project updates or to stay up to date on weekly progress, visit go.lovgov.org/Madison Avenue. The project is anticipated to be fully completed by December 2025, weather permitting. Residents who wish to sign up for the project newsletter or contact the project team can email PublicWorksInfo@cityofloveland.org or call 970-962-3669.
About
The Madison Avenue Corridor Improvement Project aims to improve safety, mobility, and infrastructure along a vital north-south route between 29th and 37th Streets. As one of the city’s most traveled corridors, Madison Avenue connects neighborhoods, schools, parks, and major arterials, including US 287. This project will modernize the corridor by adding buffered bike lanes, new sidewalks, and a new roundabout at 37th Street—all designed to support safer travel for drivers, pedestrians, and cyclists alike. In addition to improving traffic flow, the project will add a feature of public art by Art in Public Places. Construction is expected to be completed by December 2025.
Project Funding
The Madison Avenue Corridor Improvement Project is funded through a combination of the City of Loveland’s General Fund and Capital Expansion Fees (CEFs). From 2019 to 2024, approximately 20% of the project funding came from the General Fund, while the remaining 80% was provided through CEFs. Appropriations for the project began in 2019, with design services completed in 2021. The construction contract was awarded in May 2025, following a competitive bidding process.
Share Weekly project updates 7/28/2025 - 08/01/2025 on Facebook
Share Weekly project updates 7/28/2025 - 08/01/2025 on Linkedin
Email Weekly project updates 7/28/2025 - 08/01/2025 link
Hello, Loveland!
Soft spots in the roundabout area were successfully identified and corrected. While the soil quality wasn't as expected, the project team quickly implemented a solution that ensured a long-term stable foundation. This added some extra time and effort, but the roundabout remains on track to open by October 2025.
Most of the road base has now been installed in the roundabout, bringing us one step closer to paving.
Looking ahead:
Complete the final section of road base inside the roundabout.
Begin forming and pouring the curbs and gutters around the roundabout.
Starting Monday, August 4, crews will begin removing the asphalt from Madison Avenue between Hem Fir and the new roundabout. Adjacent property owners whose access is only available on Madison Avenue have been notified.
Installation of 450 feet of new waterline just north of Hem Fir will begin. Once installed and tested, this line will be connected to the system, allowing the old waterline to be safely abandoned. Any necessary water shutoffs will be communicated in advance by Loveland Utilities.
Utility relocation work for Power, Pulse, and Comcast continues south of Seven Lakes Drive.
Please refer to the photos below for a visual update of progress.
Drone overview of the Madison Avenue and 37th Street intersection on June 11, 2025
Drone overview of the newly formed roundabout at Madison Avenue and 37th Street on Aug.1, 2025
Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link)(External link)(External link). Thank you for your patience as we complete these improvements!
Share Weekly project updates 7/21/2025 - 7/25/2025 on Facebook
Share Weekly project updates 7/21/2025 - 7/25/2025 on Linkedin
Email Weekly project updates 7/21/2025 - 7/25/2025 link
Hello, Loveland!
- Grading work continues for the new roundabout, with crews addressing soft spots caused by recent rain. As a result, some planned activities have been delayed by a few days.
- Storm sewer and irrigation pipe installation in the roundabout area is now complete, and tree removals have begun throughout the entire project area.
Looking ahead:
Utility relocations will continue south of the roundabout toward 29th Street.
Traffic communications conduit will be installed within the roundabout area.
Crews will begin placing new road base in preparation for concrete curb and gutter installation.
Pavement removal on Madison Avenue, between 29th Street and Seven Lakes Drive, will be scheduled soon. Adjacent property owners with access only from Madison Avenue will be notified in advance of this work. The project team will maintain access for all adjacent property owners.
Please refer to the photos below for a visual update of progress.
Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link)(External link). Thank you for your patience as we complete these improvements!
Share Weekly project updates 7/14/2025 - 7/18/2025 on Facebook
Share Weekly project updates 7/14/2025 - 7/18/2025 on Linkedin
Email Weekly project updates 7/14/2025 - 7/18/2025 link
Hello, Loveland!
- Power and Fiber Optic utility relocations at the roundabout were completed and are continuing along Madison south of the new roundabout.
- Grading work continues in the roundabout.
- Work was slowed a little due to rain during the middle of the week, but the circle and approaches are taking shape.
- Storm sewer and irrigation pipe installation started.
Looking ahead:
- Utility relocations continue south of the roundabout towards 29th Street.
- Finish underground work (storm sewer pipe, irrigation pipe, and traffic conduit) in the roundabout.
- Grading work continues, and the road base should start and be delivered and installed. This is the layer directly underneath the pavement and is an important structural component of the roadway.
- Removal of pavement south of the roundabout is slated to begin Monday, July 28. Shortly after, there will be waterline and storm sewer work north of Hem Fir.
- Weather permitting, we will begin pouring concrete for the curb and gutter that'll outline the roundabout the last week of July.
Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link). Thank you for your patience as we complete these improvements!