Share Weekly project updates 10/27/2025 - 10/31/2025 on Facebook
Share Weekly project updates 10/27/2025 - 10/31/2025 on Linkedin
Email Weekly project updates 10/27/2025 - 10/31/2025 link
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (November 3 – November 7):
- One stormwater culvert was completed
- Stormwater inlets were formed and poured
- Sanitary sewer upgrades were completed
Looking ahead:
- One final stormwater culvert will be placed
- Roadway fill and grading will continue On Madison Avenue
- Asphalt will be removed near 29th Street
- Concrete will be removed near 29th Street
- Preparation will continue for cement treatment of subgrade
Please refer to the photos below for a visual update of progress.
Stormwater lid installation placement
Sanitary sewer excavation on Madison Avenue Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link). Thank you for your patience as we complete these improvements!
Share Weekly project updates 10/20/2025 - 10/24/2025 on Facebook
Share Weekly project updates 10/20/2025 - 10/24/2025 on Linkedin
Email Weekly project updates 10/20/2025 - 10/24/2025 link
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (October 27 – October 31):
- Stormwater installation has continued up towards Seven Lakes Drive
- Comcast has relocated their lines
- Utility poles have been removed
Looking ahead:
- Stormwater culverts will be placed
- Stormwater inlets will be formed and poured
- Sanitary sewer upgrades will be completed
Please refer to the photos below for a visual update of progress.
Stormwater manhole placement on Madison Avenue
Stormwater inlet tie-in on Madison Avenue Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
Share Weekly project updates 10/13/2025 - 10/17/2025 on Facebook
Share Weekly project updates 10/13/2025 - 10/17/2025 on Linkedin
Email Weekly project updates 10/13/2025 - 10/17/2025 link
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (October 20 – October 24):
- Stormwater installation has continued near Hem Fir
- Power vault at 29th Street and Madison Avenue has been relocated
Looking ahead:
- Stormwater installation will continue northward
- Comcast will continue relocating lines
- Utility poles will begin being removed
Please refer to the photos below for a visual update of progress.
New utility vault being placed on 29th Street and Madison Avenue.
Stormwater infrastructure being installed near Hem Fir on Madison Avenue. Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
Share Weekly project update 10/6/2025 - 10/10/2025 on Facebook
Share Weekly project update 10/6/2025 - 10/10/2025 on Linkedin
Email Weekly project update 10/6/2025 - 10/10/2025 link
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (October 13 – October 17):
- Traffic signal updates on 29th Street and Madison Avenue have been completed
- Waterline updates have been completed
- Installation of waterline board insulation has been completed
- Stormwater updates are beginning near Hem Fir
- Power continued to be relocated
- Comcast has been relocated under 29th Street
Looking ahead:
- Stormwater installation will continue near Hem Fir
- Installation of pedestrian push buttons at 29th Street and Madison Avenue
- Power vault will be relocated on 29th Street and Madison Avenue
- Cement treatment may begin on Madison Avenue
Monroe Bridge County Project:
Please refer to the photos below for a visual update of progress.
Stormwater materials off in the distance being prepared for installation.
Waterline installation on Madison Avenue Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
Share Weekly project update 9/29/2025 - 10/03/2025 on Facebook
Share Weekly project update 9/29/2025 - 10/03/2025 on Linkedin
Email Weekly project update 9/29/2025 - 10/03/2025 link
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (October 6 – October 10):
- Subgrade and fill have continued on Madison between 29th and 37th Streets
- Traffic signal updates on 29th and Madison have continued
- Water hydrants have been replaced
- Installation of waterline board insulation
- Stormwater updates are beginning
- Electrical utilities continue to be relocated
Looking ahead:
- Waterline updates should wrap up
- Stormwater installation will begin near Hem Fir
- Comcast relocations will occur under 29th Street
- Traffic signal updates should be completed
- Electrical utility relocations adjacent to 29th Street should be completed
37th Street County Project: Larimer County will be completing a street rehabilitation project by removing the old asphalt on 37th Street between Monroe and Madison Avenues. The road between Monroe and Madison Avenues is owned by Larimer County. For more information about this upcoming work, please see Larimer County’s website at https://www.larimer.gov/roads.
Please refer to the photos below for a visual update of progress.
Installation of 29th Street traffic signal and electrical work.
Hydrant removals were completed and new hydrants were installed on Madison Avenue
Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
Share Weekly project updates 9/22/2025 - 9/26/2025 on Facebook
Share Weekly project updates 9/22/2025 - 9/26/2025 on Linkedin
Email Weekly project updates 9/22/2025 - 9/26/2025 link
Hello, Loveland!
Here’s last week's update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned this week (September 29 – October 3):
- Roundabout has been opened to the public
- Stabilization for erosion control applied to banks
- Excavation and asphalt removals continued on Madison
- Waterline work continued near Seven Lakes
Looking ahead:
- Subgrade preparation and fill
- Traffic signal updates on 29th and Madison Avenue
- Waterline updates will continue northward
- Waterline updates near Seven Lakes
- Installation of waterline board insulation
Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
Share Madison Avenue Construction Update - August Recap on Facebook
Share Madison Avenue Construction Update - August Recap on Linkedin
Email Madison Avenue Construction Update - August Recap link
Madison Avenue Construction Update – August Recap
Throughout August, construction for the Madison Avenue Corridor Improvement Project moved forward with several key milestones.
- During the week of August 4–8, crews poured the curb and gutter concrete along the outer edges of the roundabout and installed the median islands. A section of Madison Avenue was removed to begin lowering 350 feet of waterline in preparation for future work.
- The following week, August 11–15, work continued with additional curb and gutter concrete pours inside the roundabout. Crews lowered the waterline at Hem Fir Place, while grading progressed for new sidewalk sections along the northeast corner. Preparations began to place median cover material, and sidewalk concrete was poured around the roundabout.
- From August 18–25, the waterline lowering advanced north of Hem Fir Place. Grading and sidewalk construction remained a focus, with crews continuing to pour new sidewalk concrete around the roundabout.
- Finally, during the week of August 25–29, the concrete pavement around the roundabout was completed and asphalt paving began at the roundabout entrances, marking an important step toward the project’s completion.
37th Street roundabout open for traffic
The project team is pleased to announce that the 37th Street roundabout is officially opened to drivers, pedestrians and cyclists. Madison Avenue, however, remains fully closed between 29th Street and 37th Street and will continue to be under full closure until the project is completed at the end of the year. During this time, crews will continue with utility upgrades, road and sidewalk connectivity improvements. With the roundabout now open, traffic may travel along 37th Street from either Boise or Monroe Avenues, and Seeley Drive is also accessible to the nearing neighborhood.
A sculpture of a dandelion will be installed in October at the center of the roundabout by Art in Public Places and the remaining landscape near the roundabout will be installed in spring 2026. The sculptor is fully funded by Art in Public Places.
Before construction started at the Madison Avenue and 37th Street intersection in July 2025.
During construction for the roundabout in August 2025.
Construction completed for the roundabout in September 2025.
Safety during construction
As construction continues along Madison Avenue, the road remains an active construction zone. While the site roundabout is partially finished, the project team urges pedestrians, cyclists and commuters to remain vigilant of posted signage and not to enter the active worksite if they are not an adjacent property owner.
Traffic and Detours:
Madison Avenue remains closed between 29th and 37th Streets. Local access to Madison Avenue is only available for those who live or own property along Madison Avenue between 29th and 37th Streets. Commuters outside the construction limits should follow the designated detour routes by using the following streets:
- North Boise Avenue
- Monroe Avenue
- 29th Street
- 37th Street
- US 34
For project updates or to stay up to date on weekly progress, visit go.lovgov.org/Madison Avenue. The project is anticipated to be fully completed by December 2025, weather permitting. Residents who wish to sign up for the project newsletter or contact the project team can email PublicWorksInfo@cityofloveland.org or call 970-962-3669.
An updated detour map for September 19, 2025.
About
The Madison Avenue Corridor Improvement Project aims to improve safety, mobility, and infrastructure along a vital north-south route between 29th and 37th Streets. As one of the city’s most traveled corridors, Madison Avenue connects neighborhoods, schools, parks, and major arterials, including US 287. This project will modernize the corridor by adding buffered bike lanes, new sidewalks, and a new roundabout at 37th Street—all designed to support safer travel for drivers, pedestrians, and cyclists alike. In addition to improving traffic flow, the project will add a feature of public art by Art in Public Places. Construction is expected to be completed by December 2025.
Project Funding
The Madison Avenue Corridor Improvement Project is funded through a combination of the City of Loveland’s General Fund and Capital Expansion Fees (CEFs). From 2019 to 2024, approximately 20% of the project funding came from the General Fund, while the remaining 80% was provided through CEFs. Appropriations for the project began in 2019, with design services completed in 2021. The construction contract was awarded in May 2025, following a competitive bidding process.
Share Weekly project updates 9/8/2025 - 9/12/2025 on Facebook
Share Weekly project updates 9/8/2025 - 9/12/2025 on Linkedin
Email Weekly project updates 9/8/2025 - 9/12/2025 link
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (September 8 – September 12):
- Madison has been milled from 37th Street to Seven Lakes Drive.
- Median cover material has been completed.
- Waterline updates are continuing north on Madison Avenue.
- Sidewalk continues to be poured around the roundabout.
- Final grading continues for stabilization.
Looking ahead:
- Top lift of asphalt on the west, north, and east legs of the roundabout
- Roadway grading along the milled section on Madison Avenue
- Waterline updates will continue north on Madison Avenue.
- Sidewalk will continue to be poured around the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Dr.
Please refer to the photos below for a visual update of progress.
Light poles are installed around the roundabout.
Cassions are installed at the southwest corner of the roundabout.
Share Weekly project updates 9/1/2025 - 9/5/2025 on Facebook
Share Weekly project updates 9/1/2025 - 9/5/2025 on Linkedin
Email Weekly project updates 9/1/2025 - 9/5/2025 link
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (September 8 – September 12):
- Madison has been milled from 37th Street to Seven Lakes Drive
- Median cover material has been completed.
- Waterline updates are continuing northward.
- Sidewalk continues to be poured around the roundabout.
- Final grading continues for stabilization.
Looking ahead:
- Top lift of asphalt on the west, north, and east fingers of the roundabout
- Roadway grading along the milled section on Madison Avenue
- Waterline updates will continue north on Madison Avenue.
- Sidewalk will continue to be poured around the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Dr.
Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
Share Weekly project updates 8/25/2025 - 8/29/2025 on Facebook
Share Weekly project updates 8/25/2025 - 8/29/2025 on Linkedin
Email Weekly project updates 8/25/2025 - 8/29/2025 link
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (August 25 – August 29):
- Median cover material has continued.
- Waterline updates continue along the project.
- The truck apron has been completed.
- The concrete pavement for the roundabout has been poured.
- Grading continues for sidewalk sections.
- Sleeper slabs have been poured for the roundabout.
- Asphalt has begun being paved around the roundabout.
Looking ahead:
- Median cover material will be finished.
- Waterline updates will continue northward from Hem Fir.
- Sidewalk will continue to be poured around the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Drive.
Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!