Weekly project updates 11/17/2025 - 11/21/2025
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (November 24 – November 26):
- Base was laid for the roadway
- Concrete string lining was completed in areas
- Concrete curb and gutter work started
- Concrete hand forming and pouring started in areas
Looking ahead:
- Curb and gutter will continue to be poured
- Concrete hand forming and pouring will continue
- Driveways may begin being poured
Important Update: Upcoming Closure of Monroe Bridge
- Larimer County has started their bridge project
- The county anticipates closing the bridge starting Monday, December 1, 2025.
- To follow this project, visit: https://www.larimer.gov/engineering/project-status-reports/project-no-341-monroe-avenue-bridge-replacement-over-dry-creek
Please refer to the photos below for a visual update of progress.
Forming curb and gutter near the Seven Lakes entrance off of Madison Avenue
Curb installation off of Madison Avenue near the Seven Lakes entrance facing north. Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
Share Weekly project updates 11/17/2025 - 11/21/2025 on Facebook
Share Weekly project updates 11/17/2025 - 11/21/2025 on Twitter
Share Weekly project updates 11/17/2025 - 11/21/2025 on Linkedin
Email Weekly project updates 11/17/2025 - 11/21/2025 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends