Weekly project updates 11/17/2025 - 11/21/2025

Hello, Loveland!

Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (November 24 – November 26):

  • Base was laid for the roadway
  • Concrete string lining was completed in areas
  • Concrete curb and gutter work started
  • Concrete hand forming and pouring started in areas

Looking ahead:

  • Curb and gutter will continue to be poured
  • Concrete hand forming and pouring will continue
  • Driveways may begin being poured

Important Update: Upcoming Closure of Monroe Bridge

Please refer to the photos below for a visual update of progress.

Forming curb and gutter near the Seven Lakes entrance off of Madison Avenue

Curb installation off of Madison Avenue near the Seven Lakes entrance facing north.

Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!


Share Weekly project updates 11/17/2025 - 11/21/2025 on Facebook Share Weekly project updates 11/17/2025 - 11/21/2025 on Twitter Share Weekly project updates 11/17/2025 - 11/21/2025 on Linkedin Email Weekly project updates 11/17/2025 - 11/21/2025 link
#<Object:0x0000000031704780>