Weekly project updates 12/1/2025 - 12/5/2025
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (December 8 – December 12):
- Curb and gutter pouring continues
- Concrete hand forming continues
- Driveway pouring continues
Looking ahead (Weather dependent):
- Driveways will continue being poured
- Asphalt paving will begin
- Sidewalk pouring will begin
- Grading will continue
- As inclement weather approaches, it may dictate work activity and scheduling.
Monroe Avenue Bridge Replacement over Dry Creek Project:
- Larimer County has closed the Monroe Avenue bridge to begin the Monroe Avenue Bridge Replacement over Dry Creek Project. The County anticipates the bridge being closed until summer 2026. To learn more about the County's project, visit: https://www.larimer.gov/engineering/project-status-reports/project-no-341-monroe-avenue-bridge-replacement-over-dry-creek.
Please refer to the photos below for a visual update of progress.
Crews pour concrete at the entrance of a residential home. The driveways will support the new sidewalk connectivity on the westside of Madison Avenue.
Continuation of new curb and gutter on Madison Avenue. Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!