Weekly project updates 12/1/2025 - 12/5/2025

Hello, Loveland!

Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (December 8 – December 12):

  • Curb and gutter pouring continues
  • Concrete hand forming continues
  • Driveway pouring continues

Looking ahead (Weather dependent):

  • Driveways will continue being poured
  • Asphalt paving will begin
  • Sidewalk pouring will begin
  • Grading will continue
  • As inclement weather approaches, it may dictate work activity and scheduling.

Monroe Avenue Bridge Replacement over Dry Creek Project:

Please refer to the photos below for a visual update of progress.

Crews pour concrete at the entrance of a residential home. The driveways will support the new sidewalk connectivity on the westside of Madison Avenue.

Continuation of new curb and gutter on Madison Avenue.

Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!