Weekly project updates 12/8/2025 - 12/15/2025
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (December 15 – December 19):
- Concrete pouring for Curb and gutter, sidewalks and driveways continues
- 1st and 2nd lifts of asphalt are being paved
- Grading continues for sidewalks
Looking ahead (weather dependent):
- Asphalt paving will continue
- Temporary roadway striping may be completed
- Temporary striping layout will not be final striping layout
- Concrete sidewalk and grading pouring will continue
- If weather conditions stay optimal, we are preparing to complete this work with the intention of opening the road by Friday, Dec. 19. Announcement of the road opening will be shared prior to the opening.
Please refer to the photos below for a visual update of progress.
Overlooking Madison Avenue with the first run of new asphalt and new curb and gutter.

Adding the second lift of asphalt south of Seven Lakes, tack coat is applied between lifts.
Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends