Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (December 22 – December 23):

  • 1st and 2nd lifts of asphalt and temporary edges of asphalt have been completed
    • Top lift will be poured in spring 2026
  • Temporary striping layout has been marked
  • Concrete sidewalk and driveway pouring continues

Looking ahead (weather dependent):

  • Temporary striping will occur
  • Sidewalk pouring will continue
  • Madison Avenue is projected to open by Tuesday, Dec. 23, weather permitting. A press release and public announcement will be shared on Monday with more detailed information.

Please refer to the photos below for a visual update of progress.

Temporary striping is laid out on Madison Avenue. Semi-final striping will occur next week.

Sidewalk concrete paving near 29th Street facing south. Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!