Weekly project updates 12/15/2025 - 12/19/2025
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (December 22 – December 23):
- 1st and 2nd lifts of asphalt and temporary edges of asphalt have been completed
- Top lift will be poured in spring 2026
- Temporary striping layout has been marked
- Concrete sidewalk and driveway pouring continues
Looking ahead (weather dependent):
- Temporary striping will occur
- Sidewalk pouring will continue
- Madison Avenue is projected to open by Tuesday, Dec. 23, weather permitting. A press release and public announcement will be shared on Monday with more detailed information.
Please refer to the photos below for a visual update of progress.
Temporary striping is laid out on Madison Avenue. Semi-final striping will occur next week.
Sidewalk concrete paving near 29th Street facing south. Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
Share Weekly project updates 12/15/2025 - 12/19/2025 on Facebook
Share Weekly project updates 12/15/2025 - 12/19/2025 on Twitter
Share Weekly project updates 12/15/2025 - 12/19/2025 on Linkedin
Email Weekly project updates 12/15/2025 - 12/19/2025 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends