Madison Avenue Corridor Improvement Project

Share Madison Avenue Corridor Improvement Project on Facebook Share Madison Avenue Corridor Improvement Project on Twitter Share Madison Avenue Corridor Improvement Project on Linkedin Email Madison Avenue Corridor Improvement Project link

The Madison Avenue project is a critical corridor that connects to several major thoroughfares within the City of Loveland like Highway 287, E 29th Street, E 37th Street and Monroe Avenue. As one of Loveland’s major connectors, it’s an essential road to the City’s overall transportation system’s wellbeing. As the City assesses and improves multi-modal transportation, Madison Avenue is among the top roads that seeks to improve pedestrian and bicycle enhancements.

As part of Connect Loveland, the City’s Transportation Master Plan that was approved in October 2023, the current conditions of Madison Avenue range from a standard four-lane section to a two-lane rural section, which lacks essential amenities like bike lanes and sidewalks. The improvements include:

  • Buffered bike lanes on Madison Avenue from 29th Street to the newly constructed roundabout.
  • Construction of sidewalks to the east side of the road between Seven Lakes Drive to 37th Street.
  • Addition of two way left hand turn lane along Madison Avenue and left turn lane to Seven Lakes Drive.
  • A new roundabout at Madison Avenue and 37th Street with crosswalks and buffered bike lanes.
  • Additional art piece of a dandelion to Loveland’s 500+ sculptures by Loveland artist Karen Cusolito. Approved by Art in Public Places, as well as funded by the organization.

To limit public disturbances and costs, the Public Works and Utilities Departments will complete the roadway and utility improvements at the same time to lessen disruptions. The project addresses bicycle and pedestrian improvements, relocation of utilities and improvements to overhead powerlines within the corridor that have reached their lifespan.

Project Vision

To transform Madison Avenue into a safe, efficient, and multimodal corridor that enhances connectivity, improves accessibility, and supports Loveland’s long-term multimodal transportation goals. This project will upgrade infrastructure, add bike lanes and sidewalks, improve utilities, and enhance traffic flow—creating a more sustainable and inclusive transportation network for all.

Project Impacts

By early July, the City of Loveland aims to begin construction, starting with underground water and stormwater utility improvements. Once infrastructure improvements are complete, the City of Loveland will focus on surface improvements determined by the streetscape design. Between utility and streetscape improvements, the project is anticipated to take six to eight months to construct.

The intersection of Madison and 37th will be closed while the roundabout is constructed at the intersection. To facilitate detour efficiency, the intersection of 33rd and Monroe Avenue has been converted into a two-way stop from a four-way stop to accommodate the detour traffic.

Project Goals

  • Offer improved safety and transportation options for people whether they are driving, walking, or biking.
  • Focus on modes of travel – making improvements to travel lanes, bike lanes and sidewalks along the corridor.
  • Upgrades to improve safety at the intersections and along the corridor
  • Improved connectivity to US Highway 287 and beyond to Taft Avenue.
  • Effective use of City funds – combine and coordinate roadway and utility improvements and relocations to lessen public disruption.

Project Funding

  • 2019-2024 General Fund = 20%
  • 2019-2024 Capital Expansion Fees (CEF) = 80%
    • Appropriations of funds for the project began in 2019.
    • Design services for the project were completed in 2021.
    • Contracted for the project awarded in April 2021.
    • Contractor awarded for the project in May 2025.

Stay Informed

To stay informed about this project, subscribe to our email list in the "Stay Informed" section. We understand construction can cause disruptions. If you have a question about the project or would like to contact the project team, email PublicWorksInfo@cityofloveland.org or call 970-962-3669. Please allow us to respond to your requests within 24-48 hours. You may also add your question or comment in the "Questions and Answers" section. Thank you for your patience while this work is being completed.

The Madison Avenue project is a critical corridor that connects to several major thoroughfares within the City of Loveland like Highway 287, E 29th Street, E 37th Street and Monroe Avenue. As one of Loveland’s major connectors, it’s an essential road to the City’s overall transportation system’s wellbeing. As the City assesses and improves multi-modal transportation, Madison Avenue is among the top roads that seeks to improve pedestrian and bicycle enhancements.

As part of Connect Loveland, the City’s Transportation Master Plan that was approved in October 2023, the current conditions of Madison Avenue range from a standard four-lane section to a two-lane rural section, which lacks essential amenities like bike lanes and sidewalks. The improvements include:

  • Buffered bike lanes on Madison Avenue from 29th Street to the newly constructed roundabout.
  • Construction of sidewalks to the east side of the road between Seven Lakes Drive to 37th Street.
  • Addition of two way left hand turn lane along Madison Avenue and left turn lane to Seven Lakes Drive.
  • A new roundabout at Madison Avenue and 37th Street with crosswalks and buffered bike lanes.
  • Additional art piece of a dandelion to Loveland’s 500+ sculptures by Loveland artist Karen Cusolito. Approved by Art in Public Places, as well as funded by the organization.

To limit public disturbances and costs, the Public Works and Utilities Departments will complete the roadway and utility improvements at the same time to lessen disruptions. The project addresses bicycle and pedestrian improvements, relocation of utilities and improvements to overhead powerlines within the corridor that have reached their lifespan.

Project Vision

To transform Madison Avenue into a safe, efficient, and multimodal corridor that enhances connectivity, improves accessibility, and supports Loveland’s long-term multimodal transportation goals. This project will upgrade infrastructure, add bike lanes and sidewalks, improve utilities, and enhance traffic flow—creating a more sustainable and inclusive transportation network for all.

Project Impacts

By early July, the City of Loveland aims to begin construction, starting with underground water and stormwater utility improvements. Once infrastructure improvements are complete, the City of Loveland will focus on surface improvements determined by the streetscape design. Between utility and streetscape improvements, the project is anticipated to take six to eight months to construct.

The intersection of Madison and 37th will be closed while the roundabout is constructed at the intersection. To facilitate detour efficiency, the intersection of 33rd and Monroe Avenue has been converted into a two-way stop from a four-way stop to accommodate the detour traffic.

Project Goals

  • Offer improved safety and transportation options for people whether they are driving, walking, or biking.
  • Focus on modes of travel – making improvements to travel lanes, bike lanes and sidewalks along the corridor.
  • Upgrades to improve safety at the intersections and along the corridor
  • Improved connectivity to US Highway 287 and beyond to Taft Avenue.
  • Effective use of City funds – combine and coordinate roadway and utility improvements and relocations to lessen public disruption.

Project Funding

  • 2019-2024 General Fund = 20%
  • 2019-2024 Capital Expansion Fees (CEF) = 80%
    • Appropriations of funds for the project began in 2019.
    • Design services for the project were completed in 2021.
    • Contracted for the project awarded in April 2021.
    • Contractor awarded for the project in May 2025.

Stay Informed

To stay informed about this project, subscribe to our email list in the "Stay Informed" section. We understand construction can cause disruptions. If you have a question about the project or would like to contact the project team, email PublicWorksInfo@cityofloveland.org or call 970-962-3669. Please allow us to respond to your requests within 24-48 hours. You may also add your question or comment in the "Questions and Answers" section. Thank you for your patience while this work is being completed.

  • Weekly project updates 12/15/2025 - 12/19/2025

    Share Weekly project updates 12/15/2025 - 12/19/2025 on Facebook Share Weekly project updates 12/15/2025 - 12/19/2025 on Twitter Share Weekly project updates 12/15/2025 - 12/19/2025 on Linkedin Email Weekly project updates 12/15/2025 - 12/19/2025 link

    Hello, Loveland!

    Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (December 22 – December 23):

    • 1st and 2nd lifts of asphalt and temporary edges of asphalt have been completed
      • Top lift will be poured in spring 2026
    • Temporary striping layout has been marked
    • Concrete sidewalk and driveway pouring continues

    Looking ahead (weather dependent):

    • Temporary striping will occur
    • Sidewalk pouring will continue
    • Madison Avenue is projected to open by Tuesday, Dec. 23, weather permitting. A press release and public announcement will be shared on Monday with more detailed information.

    Please refer to the photos below for a visual update of progress.

    Temporary striping is laid out on Madison Avenue. Semi-final striping will occur next week.

    Sidewalk concrete paving near 29th Street facing south. Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!

  • Weekly project updates 12/8/2025 - 12/15/2025

    Share Weekly project updates 12/8/2025 - 12/15/2025 on Facebook Share Weekly project updates 12/8/2025 - 12/15/2025 on Twitter Share Weekly project updates 12/8/2025 - 12/15/2025 on Linkedin Email Weekly project updates 12/8/2025 - 12/15/2025 link

    Hello, Loveland!

    Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (December 15 – December 19):

    • Concrete pouring for Curb and gutter, sidewalks and driveways continues
    • 1st and 2nd lifts of asphalt are being paved
    • Grading continues for sidewalks

    Looking ahead (weather dependent):

    • Asphalt paving will continue
    • Temporary roadway striping may be completed
      • Temporary striping layout will not be final striping layout
    • Concrete sidewalk and grading pouring will continue
    • If weather conditions stay optimal, we are preparing to complete this work with the intention of opening the road by Friday, Dec. 19. Announcement of the road opening will be shared prior to the opening.

    Please refer to the photos below for a visual update of progress.

    Overlooking Madison Avenue with the first run of new asphalt and new curb and gutter.


    Adding the second lift of asphalt south of Seven Lakes, tack coat is applied between lifts.

    Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!

  • Weekly project updates 12/1/2025 - 12/5/2025

    Share Weekly project updates 12/1/2025 - 12/5/2025 on Facebook Share Weekly project updates 12/1/2025 - 12/5/2025 on Twitter Share Weekly project updates 12/1/2025 - 12/5/2025 on Linkedin Email Weekly project updates 12/1/2025 - 12/5/2025 link

    Hello, Loveland!

    Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (December 8 – December 12):

    • Curb and gutter pouring continues
    • Concrete hand forming continues
    • Driveway pouring continues

    Looking ahead (Weather dependent):

    • Driveways will continue being poured
    • Asphalt paving will begin
    • Sidewalk pouring will begin
    • Grading will continue
    • As inclement weather approaches, it may dictate work activity and scheduling.

    Monroe Avenue Bridge Replacement over Dry Creek Project:

    Please refer to the photos below for a visual update of progress.

    Crews pour concrete at the entrance of a residential home. The driveways will support the new sidewalk connectivity on the westside of Madison Avenue.

    Continuation of new curb and gutter on Madison Avenue.

    Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!


  • Weekly project updates 11/24/2025 - 11/28/2025

    Share Weekly project updates 11/24/2025 - 11/28/2025 on Facebook Share Weekly project updates 11/24/2025 - 11/28/2025 on Twitter Share Weekly project updates 11/24/2025 - 11/28/2025 on Linkedin Email Weekly project updates 11/24/2025 - 11/28/2025 link

    Hello, Loveland!

    Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (December 1 – December 5):

    • Crews continued with curb and gutter concrete pouring, as well as hand forming on Madison Avenue.
    • Residential driveway pouring began.
    • Holiday hours on Thanksgiving Day and the Day After Thanksgiving:
      • Work operations will resume on Monday, Dec. 1, from 7 a.m. to 7 p.m.

    Looking ahead (Weather dependent):

    • Operations to complete the concrete curb, gutter and driveways will continue to be poured along Madison Avenue.
    • Bottom lift of asphalt may begin, weather depending.
    • As asphalt operations begin, we ask community members to stay clear of the active construction zone. Heavy equipment will increase onsite as crews install asphalt on the road.
    • If snowfall is expected, operations may temporarily stall production until snowfall clears.

    Upcoming Closure of Monroe Bridge:

    Please refer to the photos below for a visual update of progress.

    To protect and preserve the new curb and gutter at the Seven Lakes entrance, blankets are placed over the concrete.
    New curb and gutter placed on the west side of Madison Avenue.

    Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!

  • Weekly project updates 11/17/2025 - 11/21/2025

    Share Weekly project updates 11/17/2025 - 11/21/2025 on Facebook Share Weekly project updates 11/17/2025 - 11/21/2025 on Twitter Share Weekly project updates 11/17/2025 - 11/21/2025 on Linkedin Email Weekly project updates 11/17/2025 - 11/21/2025 link

    Hello, Loveland!

    Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (November 24 – November 26):

    • Base was laid for the roadway
    • Concrete string lining was completed in areas
    • Concrete curb and gutter work started
    • Concrete hand forming and pouring started in areas

    Looking ahead:

    • Curb and gutter will continue to be poured
    • Concrete hand forming and pouring will continue
    • Driveways may begin being poured

    Important Update: Upcoming Closure of Monroe Bridge

    Please refer to the photos below for a visual update of progress.

    Forming curb and gutter near the Seven Lakes entrance off of Madison Avenue

    Curb installation off of Madison Avenue near the Seven Lakes entrance facing north.

    Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!


  • Weekly project updates 11/10/2025 - 11/14/2025

    Share Weekly project updates 11/10/2025 - 11/14/2025 on Facebook Share Weekly project updates 11/10/2025 - 11/14/2025 on Twitter Share Weekly project updates 11/10/2025 - 11/14/2025 on Linkedin Email Weekly project updates 11/10/2025 - 11/14/2025 link

    Hello, Loveland!

    Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (November 17 – November 21):

    • Cement treatment of the subgrade on Madison Avenue has been completed
    • The base was laid for curb and gutter

    Looking ahead:

    • Base will be laid for Madison Avenue's roadway
    • Stringline of concrete will be completed
    • Concrete curb and gutter will be poured by the equipment
    • Concrete hand form and pour will be completed in some areas

    Please refer to the photos below for a visual update of progress.

    Cement subgrade application on Madison Avenue

    Cement compaction on Madison Avenue

    Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!

  • Weekly project updates 11/3/2025 - 11/7/2025

    Share Weekly project updates 11/3/2025 - 11/7/2025 on Facebook Share Weekly project updates 11/3/2025 - 11/7/2025 on Twitter Share Weekly project updates 11/3/2025 - 11/7/2025 on Linkedin Email Weekly project updates 11/3/2025 - 11/7/2025 link

    Hello, Loveland!

    Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (November 10 – November 14):

    • The final stormwater culvert was completed
    • Roadway fill and grading are continuing
    • Asphalt has been removed near 29th Street
    • Concrete has been removed near along the project
    • Subgrade preparation has been completed

    Looking ahead:

    • Cement treatment of subgrade will be completed
      • This will save money and time instead of exchanging soil
      • While we're completing this treatment, dust clouds are likely to occur and we encourage neighbors in the surrounding area to keep their windows, garages and doors closed until the end of the week. If questions arise, please call the project hotline at 970-962-3669.
    • Road base will be laid
    • Road base will be graded in preparation of asphalt placement

    Please refer to the photos below for a visual update of progress.

    Final culvert installation on Madison Avenue

    Asphalt removal near 29th Street and Madison Avenue

    Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!


  • Weekly project updates 10/27/2025 - 10/31/2025

    Share Weekly project updates 10/27/2025 - 10/31/2025 on Facebook Share Weekly project updates 10/27/2025 - 10/31/2025 on Twitter Share Weekly project updates 10/27/2025 - 10/31/2025 on Linkedin Email Weekly project updates 10/27/2025 - 10/31/2025 link

    Hello, Loveland!

    Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (November 3 – November 7):

    • One stormwater culvert was completed
    • Stormwater inlets were formed and poured
    • Sanitary sewer upgrades were completed

    Looking ahead:

    • One final stormwater culvert will be placed
    • Roadway fill and grading will continue On Madison Avenue
    • Asphalt will be removed near 29th Street
    • Concrete will be removed near 29th Street
    • Preparation will continue for cement treatment of subgrade

    Please refer to the photos below for a visual update of progress.

    Stormwater lid installation placement

    Sanitary sewer excavation on Madison Avenue

    Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link). Thank you for your patience as we complete these improvements!

  • Weekly project updates 10/20/2025 - 10/24/2025

    Share Weekly project updates 10/20/2025 - 10/24/2025 on Facebook Share Weekly project updates 10/20/2025 - 10/24/2025 on Twitter Share Weekly project updates 10/20/2025 - 10/24/2025 on Linkedin Email Weekly project updates 10/20/2025 - 10/24/2025 link

    Hello, Loveland!

    Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (October 27 – October 31):

    • Stormwater installation has continued up towards Seven Lakes Drive
    • Comcast has relocated their lines
    • Utility poles have been removed

    Looking ahead:

    • Stormwater culverts will be placed
    • Stormwater inlets will be formed and poured
    • Sanitary sewer upgrades will be completed

    Please refer to the photos below for a visual update of progress.

    Stormwater manhole placement on Madison Avenue

    Stormwater inlet tie-in on Madison Avenue

    Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!


  • Weekly project updates 10/13/2025 - 10/17/2025

    Share Weekly project updates 10/13/2025 - 10/17/2025 on Facebook Share Weekly project updates 10/13/2025 - 10/17/2025 on Twitter Share Weekly project updates 10/13/2025 - 10/17/2025 on Linkedin Email Weekly project updates 10/13/2025 - 10/17/2025 link

    Hello, Loveland!

    Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (October 20 – October 24):

    • Stormwater installation has continued near Hem Fir
    • Power vault at 29th Street and Madison Avenue has been relocated

    Looking ahead:

    • Stormwater installation will continue northward
    • Comcast will continue relocating lines
    • Utility poles will begin being removed

    Please refer to the photos below for a visual update of progress.

    New utility vault being placed on 29th Street and Madison Avenue.

    Stormwater infrastructure being installed near Hem Fir on Madison Avenue.

    Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!

Page last updated: 23 Dec 2025, 10:38 AM