Share Weekly project updates 9/22/25 - 9/26/25 on Facebook
Share Weekly project updates 9/22/25 - 9/26/25 on Linkedin
Email Weekly project updates 9/22/25 - 9/26/25 link
Here are the project updates for next week (9/22/25-9/26/25).
The Lincoln and E. 4th Street intersection is open to the north and west. The east leg remains closed until Block 2 (Jefferson to Lincoln) is completed.
The lane closure at Lincoln and E. 3rd Street will remain in place until the week of 9/29/25.
-
Blocks 1 and 2 (Washington to Lincoln) and Block 5 (Garfield to RR Ave.) are fully closed to motorists.
- Sidewalk removals have started on Block 1 and 2 and “Phase 1B” pedestrian access has been deployed in strategic areas. Please be mindful of changing surface conditions and pedestrian routes as construction progresses.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Share FOR RELEASE: 3rd Street at Cleveland and Lincoln Avenue intersections will install crosswalks for improved pedestrian safety on Facebook
Share FOR RELEASE: 3rd Street at Cleveland and Lincoln Avenue intersections will install crosswalks for improved pedestrian safety on Linkedin
Email FOR RELEASE: 3rd Street at Cleveland and Lincoln Avenue intersections will install crosswalks for improved pedestrian safety link
City of Loveland, Colorado
MEDIA RELEASE
CONTACT: Illianna Milldrum, Communication and Engagement Specialist, 970-962-2608, Illianna.Milldrum@cityofloveland.org
3rd Street between Cleveland and Lincoln Avenues will install crosswalks for improved pedestrian safety
LOVELAND, Colo. – Sept. 15, 2025 – In coordination with the Heart Improvement Plan’s 4th Street improvements, the City of Loveland will install crosswalks at the 3rd Street and Cleveland Avenue intersection and 3rd Street and Lincoln Avenue intersection. The installation will begin today and take approximately two weeks to complete.
The project’s general working hours will be from 7 a.m. to 7 p.m., Monday through Friday. During the installation, business entrances and sidewalks remain open on 3rd Street between Cleveland and Lincoln Avenues.
Below are more specific Frequently Asked Questions that may be helpful.
Are the crosswalk improvements part of the Heart Improvement Plan?
The project team will be coordinating traffic control impacts with the Heart Improvement Plan’s 4th Street Revitalization project. To assist with traffic impacts, the installation of the crosswalks will slightly overlap the 4th Street and Lincoln Avenue work; however, construction at the 4th Street and Lincoln Avenue intersection should be completed by the end of next week, weather permitting.
Will traffic on Lincoln Avenue or Cleveland Avenue be impacted?
For the two-week duration, Lincoln Avenue traffic will be reduced to a single lane. Westbound 3rd Street traffic will be fully closed at Lincoln Avenue, with a detour available at Jefferson Avenue. A similar closure will occur at 3rd Street and Cleveland Avenue, where eastbound traffic will be rerouted to Railroad Avenue. Pedestrians will be encouraged to cross Lincoln and Cleveland Avenues at 4th Street and 1st Street through installation.
How are the crosswalk improvements funded?
The City of Loveland and Loveland Downtown Development Authority (DDA) applied for the Colorado Department of Local Affairs Revitalizing Main Streets (RMS) grant program and was awarded earlier this year. The program encourages physical activity and enhances local economic vitality in towns and cities across Colorado through funding infrastructure improvements to make walking and biking easy, yielding long-term benefits that bolster community connections. The amount awarded for the crosswalk installation was $250,000.
Why are crosswalks being installed in this area?
Based on feedback from downtown residents and businesses, this section was identified as a priority for improving pedestrian safety. A 2022 traffic study confirmed the challenges pedestrians faced when crossing 3rd Street and highlighted the need for better connectivity. The Colorado Department of Transportation agreed that crosswalks were essential in this high-pedestrian area. Once the project is complete, new bulb-out crosswalks will give pedestrians a safer, more direct connection to the Foundry Parking Garage.
How to stay in the loop?
To stay informed about the Heart Improvement Plan’s downtown construction, visit lovgov.org/HIPStreets. For questions about the crosswalk installation or to contact the project team, call the Public Works Department at 970-962-2524 or email PublicWorksInfo@cityofloveland.org.
Project Funding
The Revitalizing Main Streets (RMS) grant program was awarded to the City of Loveland and DDA earlier this year. The project was accepted with terms to have the crosswalks completed by October 2025 or else the funding would expire. The grant supports $250,000 for the installation with a 10% match from the DDA.
Share Weekly project updates 9/8/25 - 9/12/25 on Facebook
Share Weekly project updates 9/8/25 - 9/12/25 on Linkedin
Email Weekly project updates 9/8/25 - 9/12/25 link
Hello, Loveland!
Here are the project updates for next week (9/15/25-9/19/25).
- The Lincoln Avenue lane closure will be extended south to east 3rd Street for crosswalk improvements at east 3rd Street and Lincoln Avenue.
- Blocks 1 and 2 (Washington to Lincoln Avenues) and Block 5 (Garfield to Railroad Avenue) are fully closed to motorists.
- Sidewalk removals have started on Block 1.
- The east-west crosswalks at Lincoln Avenue and east 4th Street, Washington and east 4th Street will remain closed this week. Weather permitting, we anticipate restoring these crosswalks by the end of the week.
- Pedestrian detours will be in place as follows:
- At Washington and east 4th Street, foot traffic will be directed to cross Washington Avenue at east 3rd Street or east 5th Street.
- At Lincoln and east 4th Street, foot traffic will be directed to cross Lincoln Avenue at east 5 h Street.
- At Lincoln and east 3rd Street, foot traffic will be directed to cross Lincoln Avenue at east 1st Street.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share Weekly project updates 9/1/25-9/5/25 on Facebook
Share Weekly project updates 9/1/25-9/5/25 on Linkedin
Email Weekly project updates 9/1/25-9/5/25 link
Hello, Loveland!
Here are the project updates for next week (9/1/25-9/5/25):
In observance of Labor Day, there will be no construction activity on Monday, Sept. 1. Operations will resume on Tuesday, Sept. 2.
-
Blocks 1 and 2 (Washington to Lincoln Avenues ) and Block 5 (Garfield to Railroad Avenue) are fully closed to motorists.
- Northbound traffic on Lincoln Avenue/US 287 has been shifted to the west lane while work on the east side of the Lincoln Avenue and East 4th Street intersection is completed.
The east-west crosswalks at Lincoln and East 4th Street and Washington and East 4th Street will be closed for several weeks. Weather permitting, we anticipate restoring these crosswalks the week of September 15.
-
Pedestrian detours will be in place as follows:
- At Washington and East 4th Street, foot traffic will be directed to cross Washington Avenue at East 3rd Street or East 5th Street.
- At Lincoln Avenue and East 4th Street, foot traffic will be directed to cross Lincoln Avenue at East 5th Street.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share Weekly project updates 8/25/25 - 8/29/25 on Facebook
Share Weekly project updates 8/25/25 - 8/29/25 on Linkedin
Email Weekly project updates 8/25/25 - 8/29/25 link
Hello, Loveland!
Here are the project updates for next week (8/25/25-8/29/25):
- Locks 1 and 2 (Washington to Lincoln Avenues) and Block 5 (Garfield to Railroad Avenues) are fully closed to motorists.
- Water mains, storm mains, and power conduits are complete in Blocks 1 and 2.
- Water and storm mains are complete in Block 5.
- Boulder seat wall installation on Block 2.
- Concrete curb returns at Lincoln and 4th Street and Washington and 4th Street.
- Power conduits in Block 5.
- Crews are finishing the west side of Lincoln Avenue and the west lane of Lincoln will be paved this week (weather dependent). Once the west lane is paved, traffic will be shifted to the west lane on Lincoln Avenue while the east side is being completed.
- Power conduit is starting in Block 5.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org(External link)(External link)(External link)(External link)(External link)(External link) or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share Weekly project updates 8/11/25 - 8/15/25 on Facebook
Share Weekly project updates 8/11/25 - 8/15/25 on Linkedin
Email Weekly project updates 8/11/25 - 8/15/25 link
Hello, Loveland!
Here are the project updates for this week (8/18/25-8/22/25):
- Blocks 1 and 2 (Washington to Lincoln Avenues) and Block 5 (Garfield to Railroad Avenue) are fully closed to motorists.
- Concrete work, conduit installation, and irrigation lines.
- Crews are completing utilities, curb returns, and temporary sidewalks on the west side of Lincoln Avenue.
- One east to west and one north to south crosswalk has been maintained at the intersection.
- Storm sewer installation on boulder seat walls/art pedestals on Block 5.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org(External link)(External link)(External link)(External link)(External link) or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share FOR RELEASE: Found on Fourth: History Unearthed in the Heart of Downtown Loveland on Facebook
Share FOR RELEASE: Found on Fourth: History Unearthed in the Heart of Downtown Loveland on Linkedin
Email FOR RELEASE: Found on Fourth: History Unearthed in the Heart of Downtown Loveland link
Found on Fourth: History Unearthed in the Heart of Downtown Loveland
Digging into Downtown Loveland’s history…literally
Loveland, Colo. — Aug. 14, 2025 — Construction crews working on the Heart Improvement Plan in Downtown Loveland are uncovering more than just old infrastructure—they’re unearthing pieces of the city’s past.
As 4th Street undergoes revitalization, we expected that crews would discover a few unexpected artifacts buried beneath the surface. So far, the findings have amounted to old bottles, cans, wooden water pipes, and other historic bricks that offer a glimpse into Loveland’s early days.
One particularly notable find: a large concrete column discovered directly beneath the center of the intersection of 4th Street and Lincoln Avenue. When City staff started going through historic photos to see what it could be, they discovered that it once served as the foundation for a flagpole in the center of the street. This flagpole was erected in 1918 to celebrate Loveland's participation and success in a Liberty Loan campaign during World War I. Later photos show that the flagpole was removed and the same base served as one of Loveland’s first traffic lights with one central light in the intersection.
This piece of Loveland’s civic history has been carefully removed and placed on public display on 4th Street near Thompson Park, commonly known as Pocket Park. Curious community members are encouraged to stop by and see the artifact for themselves. The concrete base will be transported to a Loveland Recycle Center (400 N Wilson Ave, Loveland, CO 80537) facility the week of August 25.
These discoveries are fueling a new exhibit in the works at the Loveland Museum, titled “Found on Fourth,” which will showcase the artifacts and tell the story of the history beneath our feet. The Heart Improvement Plan team, in collaboration with the museum, is currently gathering artifacts and historical materials to bring this exhibit to life in fall of 2026.
As part of the effort, the team is seeking historic photos of 4th Street and downtown Loveland. Community members who have vintage images or relevant materials are encouraged to share them by contacting lwaneka@lovelandpartnership.org.
“We knew this project would reveal old infrastructure, but it’s really fun to also uncover small meaningful pieces of the city’s past,” said Abby Powell, assistant director, Downtown Loveland District. “It’s a powerful reminder that as we build toward Downtown Loveland’s future, we’re always looking back on the foundations of its history.”
Stay tuned for more updates on the exhibit and the transformation of 4th Street as Loveland continues to build forward—while honoring what lies beneath.
Additional project details including construction phasing maps, images and other project updates, can be found at lovgov.org/HIPStreets. To stay informed throughout construction, stakeholders can sign up for the Heart Improvement Plan project newsletter at go.lovgov.org/SubscribetoHIP. For questions about this project or to contact the project team, call Public Works at 970-962-2524 or email HIPStreets@CityofLoveland.org.
About
In 2009, the City of Loveland developed the conceptual plan for the Heart Improvement Plan (HIP Streets), which explored opportunities to enhance the streets within the historic core of Downtown Loveland. In 2017, after gathering public input, the plan was modernized to include a thoughtful and cost-effective approach to revitalizing 19 core blocks of Downtown Loveland. The first phase of the Heart Improvement Plan – the 4th Street Revitalization – addresses the five blocks along 4th Street that extend from N. Garfield Avenue to N. Washington Avenue. The current effort has the City’s Public Works Department focused on improving 4th Street through streetscape enhancements, while the City of Loveland Water and Power Department works on upgrades to the utility infrastructure beneath the road. As this project is a significant effort, the City of Loveland and the Loveland Downtown Development Authority (DDA) have come together to finally bring this portion of the Heart Improvement Plan to fruition.
Project Funding
The Loveland City Council, with a unanimous vote, approved the Certificates of Participation (COPs) financing method providing funding for the Heart Improvement Plan’s 4th Street Revitalization project on Tuesday, Nov. 19, 2024. The project will be funded using a combination of Utility Enterprise Funds and COPs. Utility Enterprise Funds (Stormwater, Water, and Power) will provide $12 million of the project cost, with the remaining $12.5 million funded by COPs. The total estimated program cost for the project is $24.5 million. No General Funds will be utilized or allocated to construct this project.
Share Weekly project updates 8/04/25 - 8/08/25 on Facebook
Share Weekly project updates 8/04/25 - 8/08/25 on Linkedin
Email Weekly project updates 8/04/25 - 8/08/25 link
Hello, Loveland!
Here are the project updates for this week (8/4/25-8/8/25):
- Blocks 1 and 2 (Washington to Lincoln Avenues) and Block 5 (Garfield to Railroad Avenue) are fully closed to motorists.
- Crews will begin paving Block 1 (Washington to Jefferson Avenues) next week!
- Crews will continue conduit installation in Block 2 (Jefferson to Lincoln Avenues) next week. Completing the conduit will allow for seat wall installation to resume.
- Crews are completing utilities and curb returns on the west side of Lincoln Avenue. Traffic has been switched to the east/northbound lane to provide room to work.
- Storm sewer installation on Block 5.
- Crews will begin sidewalk removal in preparation for boulder seat wall installation on Block 05.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org(External link)(External link)(External link)(External link) or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share Weekly project updates 7/28/25 - 8/1/2025 on Facebook
Share Weekly project updates 7/28/25 - 8/1/2025 on Linkedin
Email Weekly project updates 7/28/25 - 8/1/2025 link
Hello, Loveland!
Here are the project updates for this week (7/28/25-8/1/25):
- Blocks 1 and 2 (Washington to Lincoln Avenues) and Block 5 (Garfield to Railroad Avenues) are fully closed to motorists.
- Curb and gutter is complete on Block 1 and crews are fine grading the surface in preparation for concrete paving.
- Concrete work, seat wall installation and conduit installation continue in Block 2.
- Traffic will be switched to the east/northbound lane on Lincoln Avenue at 4th Street next week as utility work progresses west across the intersection.
- Storm sewer installation in Block 5.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org(External link)(External link)(External link) or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share Weekly project updates 7/28/25 - 8/1/25 on Facebook
Share Weekly project updates 7/28/25 - 8/1/25 on Linkedin
Email Weekly project updates 7/28/25 - 8/1/25 link
Hello, Loveland!
Here are the project updates for this week (7/28/25-8/1/25):
- Blocks 1 and 2 (Washington to Lincoln Avenues) and Block 5 (Garfield to Railroad Avenue) are fully closed to motorists.
- Crews will continue concrete work (island curbing and curb and gutter) on Blocks 1 and 2.
- The Lincoln Avenue at 4th Street intersection will remain in a one-lane configuration while crews replace utilities across the intersection.
- The waterline going across Lincoln Avenue is complete and crews are installing storm and power conduit across the intersection.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org(External link)(External link) or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!