Weekly project update 6/1/26 - 6/7/26
Hello Stakeholders!
Here are the project updates for the week of 6/1/26 – 06/7/26:
-
Cleveland Avenue
- Concrete work has been completed on the south side of Cleveland at the 4th Street intersection, and traffic lanes and on-street parking are now open.
- Concrete work has been completed on the south side of Cleveland at the 4th Street intersection, and traffic lanes and on-street parking are now open.
-
Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Sidewalk and boulder seatwall work continues. Concrete paving is nearing completion.
-
Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Electrical conduit and light pole foundations are nearing completion.
- Grading begins in preparation for concrete bollard bands and paving.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Share Weekly project update 6/1/26 - 6/7/26 on Facebook
Share Weekly project update 6/1/26 - 6/7/26 on Twitter
Share Weekly project update 6/1/26 - 6/7/26 on Linkedin
Email Weekly project update 6/1/26 - 6/7/26 link