  • Lincoln Avenue
    • West on-street parking closures between E. 3rd Street and Sweetheart Alley.
    • West lane closure at E. 4th Street: Daily (Monday through Friday) from 8:30 AM – 3:30 PM.
  • Block 3 (Lincoln to Cleveland Ave.)
    • Block remains closed to vehicle traffic; businesses are open to pedestrian access.
    • Boulder seatwalls, irrigation installations and concrete work.
  • Block 4 (Cleveland to N. Railroad Ave.)
    • Block remains closed to vehicle traffic; businesses are open to pedestrian access.
    • Storm sewer, power conduit and light pole base installations.
  • Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
    • Daily/workday closures and limited access.
    • Electric meter replacements and transformer upgrades.
  • Backstage Alley (Lincoln to Cleveland Ave.) (non-project related work)
    • Daily/workday closures and limited access.
    • CenturyLink conduit installations.

Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.

Thank you for your continued patience and support.


Share Weekly project update 5/11/26 - 5/17/26 on Facebook Share Weekly project update 5/11/26 - 5/17/26 on Twitter Share Weekly project update 5/11/26 - 5/17/26 on Linkedin Email Weekly project update 5/11/26 - 5/17/26 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>