Weekly project update 6/8/26 - 6/14/26

Hello Stakeholders!

Here are the project updates for the week of 6/8/26 - 6/14/26:

  • Block 3 (Lincoln to Cleveland Ave.)
    • Block remains closed to vehicle traffic; businesses are open to pedestrian access.
    • Boulder seatwalls, concrete work and paver installations.
  • Block 4 (Cleveland to N. Railroad Ave.)
    • Block remains closed to vehicle traffic; businesses are open to pedestrian access.
    • Concrete work, streetlights and underground tank mitigation.
  • Lincoln Avenue (non-project related work)
    • Alternating lane shifts.
    • Fiber installations.

Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.

Thank you for your continued patience and support.