Weekly project update 4/27/26 - 5/3/26
Hello Stakeholders!
Here are the project updates for this week (4/27/26-5/3/26).
- Crews will occasionally begin work as early as 5-6 AM to install building thresholds before businesses open.
- Block 1 (Washington to Jefferson Ave.)
- On-street parking closed.
- Block will be closed to vehicles for approximately one day for landscaping installations. Sidewalks will remain open.
- Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Boulder seatwalls, concrete and electric work.
- Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Storm sewer and power conduit installations.
- Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Daily/workday closures and limited access.
- Electric meter replacements and transformer upgrades.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Share Weekly project update 4/27/26 - 5/3/26 on Facebook
Share Weekly project update 4/27/26 - 5/3/26 on Twitter
Share Weekly project update 4/27/26 - 5/3/26 on Linkedin
Email Weekly project update 4/27/26 - 5/3/26 link