Weekly project update 6/22/26 - 6/28/26

Dear Stakeholders,

Project updates for the week 6/22 - 6/28/26 are as follows:

  • Block 2 (Jefferson to Lincoln Ave.)
    • Roadway and parking will be closed daily on 6/22 & 6/23 for catenary lighting installations.
  • Block 1 (Washington to Jefferson Ave.)
    • Roadway and parking will be closed daily on 6/24 & 6/25 for catenary lighting installations.
  • Block 1 & 2 (Washington to Lincoln Ave.)
    • Intermittent daily closures of parking and lane shifts for conduit installations.
  • Block 3 (Lincoln to Cleveland Ave.)
    • Block remains closed to vehicle traffic; businesses are open to pedestrian access.
    • Boulder seatwalls, concrete work and paver installations.
  • Block 4 (Cleveland to N. Railroad Ave.)
    • Block remains closed to vehicle traffic; businesses are open to pedestrian access.
    • Concrete work and electric conduit.
  • Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
    • Closed.