Weekly project update 6/22/26 - 6/28/26
Dear Stakeholders,
Project updates for the week 6/22 - 6/28/26 are as follows:
-
Block 2 (Jefferson to Lincoln Ave.)
- Roadway and parking will be closed daily on 6/22 & 6/23 for catenary lighting installations.
-
Block 1 (Washington to Jefferson Ave.)
- Roadway and parking will be closed daily on 6/24 & 6/25 for catenary lighting installations.
-
Block 1 & 2 (Washington to Lincoln Ave.)
- Intermittent daily closures of parking and lane shifts for conduit installations.
-
Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Boulder seatwalls, concrete work and paver installations.
-
Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Concrete work and electric conduit.
-
Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
- Closed.
Share Weekly project update 6/22/26 - 6/28/26 on Facebook
Share Weekly project update 6/22/26 - 6/28/26 on X (formerly Twitter)
Share Weekly project update 6/22/26 - 6/28/26 on Linkedin
Email Weekly project update 6/22/26 - 6/28/26 link