Weekly project update 5/25/26 - 5/31/26

Hello Stakeholders!

Here are the project updates for the week of 5/25/26-5/31/26:

  • No work Monday, May 25th in observance of Memorial Day
  • Cleveland Avenue
    • West on-street parking closures between E. 4th and E. 5th Streets.
    • East on-street parking closures between Backstage Alley and E. 6th Street.
    • East/southbound lane closure at E. 4th Street daily from 8:30 AM – 3:30 PM; open at night/early mornings.
  • Block 3 (Lincoln to Cleveland Ave.)
    • Block remains closed to vehicle traffic; businesses are open to pedestrian access.
    • Boulder seatwalls, electric conduit and concrete work, including panel replacements in the roadway.
  • Block 4 (Cleveland to N. Railroad Ave.)
    • Block remains closed to vehicle traffic; businesses are open to pedestrian access.
    • Boulder seatwalls and streetlight bases.
  • Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
    • Power work is complete and the alley is reopened.
    • A dumpster will still be present behind 209 E. 4th St.
  • Backstage Alley (west of Cleveland Ave.) (non-project related work)
    • Daily/workday closures and limited access.
    • CenturyLink conduit installations.
  • Cleveland Ave. and E 6thSt. (non-project related work)
    • Utility investigations and potholing work is complete.

Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.

Thank you for your continued patience and support.