Share on Facebook
Share on Linkedin
Email this link
City of Loveland, Colorado
MEDIA RELEASE
CONTACTS: Kim Overholt, Communications and Engagement Manager, 970.962.3268 | kimberly.overholt@cityofloveland.org
Illianna Milldrum, Communications and Engagement Specialist, Public Works, 970.962.2608 | illianna.milldrum@cityofloveland.org
Garfield Harrison Storm Drainage Improvements Construction Ends for 2023
Road, sidewalk, and landscape improvements completed
LOVELAND, Colo. – Oct. 10, 2023 – The City of Loveland has ended construction early of the Garfield Harrison Storm Drainage Improvements Project. Road paving, curb and gutter work and landscaping tasks were completed. Construction will restart in spring 2024.
This multi-year project is designed to implement several improvements to infrastructure in the area including:
• Replacing and upgrading existing stormwater infrastructure to address existing drainage issues and meet current stormwater standards.
• Install 18- to 60-inch diameter storm sewer pipes.
• Replace existing waterlines and valves to address aging infrastructure.
• Replace pavement including asphalt patching, milling, overlays, or full street reconstruction where project components are installed.
• Rehabilitate and replace concrete as well as add necessary ADA improvements.
• Provide stormwater quality treatment measures within the stormwater system.
The City has contracted Connell Resources as the project contractor and ICON Engineering for project design. The total project will be funded by the Stormwater, Water and Power Enterprise Funds. This project is part of the Stormwater Master Plan as well as the Water and Power Capital Improvement Program.
Additional project emails including detour maps, images and other project updates, can be found at letstalkloveland.org/garfieldharrisonproject.
Share on Facebook
Share on Linkedin
Email this link
The Garfield Harrison Storm Drain Project work activities for this coming week (9/3-9/9) include:
- No work this holiday weekend.
- Work will resume on Tuesday, 9/5.
- Concrete, landscape, and paving crews are finalizing restoration.
- Final paving is planned for next Saturday, September 9th.
- Smaller punchlist items will be addressed over the next few weeks as they are identified.
As a reminder, landscape crews will be in the project area until all yards are restored. If a damaged sprinkler is missed, residents are assured the contractor will still be available to quickly respond even after crews pull out.
Share on Facebook
Share on Linkedin
Email this link
The Garfield Harrison Storm Drain Project work activities for this coming week (8/28-9/1) include:
- Concrete, landscape, and paving crews are hard at work for the next few weeks finalizing this phase of the project.
- Some waterline work is ongoing in different locations.
- Crews are also identifying streets for repair near to the project site throughout the neighborhood.
Weather permitting, work activities are Monday-Friday, 7 a.m. to 5 p.m.
As a reminder, landscape crews will be in the project area until all yards are restored. If a damaged sprinkler is missed, residents are assured the contractor will still be available to quickly respond even after crews pull out.
Share on Facebook
Share on Linkedin
Email this link
The Garfield Harrison Storm Drain Project work activities for this coming week (8/14-8/18) include:
- Concrete replacements are still ongoing for a couple more weeks; however, pipe installation is largely complete for this year.
- Bottom and top mat paving will be ongoing for the next couple weeks also.
- The end of this month will include punch-list items and then the Garfield Harrison Project will be back for Phase 3 next spring.
Weather permitting, work activities are Monday-Friday, 7 a.m. to 5 p.m.
Share on Facebook
Share on Linkedin
Email this link
The Garfield Harrison Storm Drain Project work activities for this coming week (8/7-8/11) include:
- Completion of Phase 2 is getting close! Work will continue a couple more weeks and then construction activities will begin winding down.
- Waterline work will finish next week on W. 5th Street, followed by concrete repairs and improvements.
- Once roadway work is complete, our landscape contractor will begin restoring and repairing disturbed areas behind curbs and in yards.
Weather permitting, work activities are Monday-Friday, 7 a.m. to 5 p.m.
Share on Facebook
Share on Linkedin
Email this link
The Garfield Harrison Storm Drain Project work activities for this coming week (7/31-8/4) include:
- Crews are busy working on water and storm sewer lines in 5th Street. We’re getting close to the finish line of Phase 2.
- Paving will begin with bottom mat at various locations starting Monday, 7/31.
- Concrete repairs are ongoing.
- Dust is a problem right now with the drier weather, so crews are out at least twice a day watering the construction zone.
Weather permitting, work activities are Monday-Friday, 7am to 5pm.
Share on Facebook
Share on Linkedin
Email this link
The Garfield Harrison Storm Drain Project work activities for this coming week (7/24-7/28) include:
- Storm sewer and waterline installation continues on 5th Street. Progress has been outstanding and this phase of the project should be nearing completion in September.
- Paving is planned at the end of the month for numerous areas where work has completed.
- Concrete repairs and ADA improvements are ongoing throughout the construction zone.
Weather permitting, work activities are Monday-Friday, 7 a.m. to 5 p.m.
Share on Facebook
Share on Linkedin
Email this link
The Garfield Harrison Storm Drain Project work activities for this coming week (7/17-7/21) include:
- Crews are working on the waterline installation on W. 5th Street. Next week they will be working between Franklin Avenue and Colorado Avenue.
- Crews are also working on the storm sewer installation on Colorado Avenue. Work will continue between W. 4th Street and W. 5th Street.
- Bottom mat paving will be upcoming the week of July 24th, at W. 4th Street and Logan Avenue.
Weather permitting, work activities are Monday-Friday, 7am to 5pm.
Share on Facebook
Share on Linkedin
Email this link
The Garfield Harrison Storm Drain Project work activities for this coming week (7/10-7/14) include:
- Storm sewer installation will continue on 4th Street, west of Colorado Avenue.
- Paving will occur along 4th Street and Logan Avenue.
- Waterline installation will continue on 5th Street.
- Concrete repairs of curb, gutter, and sidewalk continue, including the installation of ADA-compliant handicap ramps at intersections.
Weather permitting, work activities are Monday-Friday, 7am to 5pm.
Share on Facebook
Share on Linkedin
Email this link
The Garfield Harrison Storm Drain Project work activities for this coming week (6/5-6/9) include:
- Storm sewer and waterline crews are continuing to work on 4th Street and making good progress.
- Concrete curb, gutter, and sidewalk repairs are ongoing through next week.
- Bottom mat paving is to occur today or possibly Monday depending on weather at 4th Street & Sheridan Avenue.
Weather permitting, work activities are Monday-Friday, 7am to 5pm.