Project Updates for 3/16/26 - 3/20/26
Below are project updates from this week, as well as for the upcoming week (March 16th - 20th):
- Two Connell crews were on site this week installing inlets. One crew will remain next week to complete installation of the final three inlets.
- The concrete crew has been working closely behind the inlet crews, restoring curb, gutter, and sidewalks.
- The concrete crew will continue pouring curb, gutter, and sidewalk sections around the inlets next week.
- The pipe crew on site will complete installation of the remaining three inlets on Roosevelt Avenue, 10th Street, and 11th Street next week.
- A cleanup crew will begin working behind the construction crews to prepare roadway sections for the bottom lift of asphalt.
- Potholing and saw cutting will begin on West 10th Street between Colorado Avenue and Douglas Avenue starting Monday. A pipe crew will then move in to begin demolition, pipe installation, and reconstruction of that section of roadway. Flyers have been distributed to all 130 nearby residents.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Share Project Updates for 3/16/26 - 3/20/26 on Facebook
Share Project Updates for 3/16/26 - 3/20/26 on Twitter
Share Project Updates for 3/16/26 - 3/20/26 on Linkedin
Email Project Updates for 3/16/26 - 3/20/26 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends