- The main crew completed pipe installation on Roosevelt Avenue, turned onto 11th Street, and is progressing toward McKinley Avenue.
- The second crew finished installing pipe and inlets at Harrison Avenue and 10th Street and has moved west to Roosevelt Avenue and 10th Street. They are currently installing inlets on the south side of the roadway.
- The concrete crew has returned to the site and began forming and pouring concrete at the four inlets at Harrison Avenue and 10th Street. Sidewalk work is scheduled for next week. They will follow behind the second crew to complete curb, gutter, and sidewalk work once inlets are installed.
- The main crew will continue installing pipe toward McKinley Avenue, then complete the section west of Roosevelt Avenue on 11th Street. If time allows, they will also install inlets along 11th Street.
- The second crew will continue installing pipe and inlets along 10th Street and Roosevelt Avenue.
- The concrete crew will continue working directly behind the second crew to complete final concrete improvements.

Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.
Share Project Updates for 2/23/26 - 2/27/26 on Facebook
Share Project Updates for 2/23/26 - 2/27/26 on Twitter
Share Project Updates for 2/23/26 - 2/27/26 on Linkedin
Email Project Updates for 2/23/26 - 2/27/26 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends