Weekly Project Updates 2/9/26 - 2/13/26
Below are project updates from this week, as well as for the upcoming week (February 9th - 13th):
- Crews began work at the intersection of Roosevelt Avenue and 10th Street and are currently working mid-block toward Barnes Place at the manhole location.
- Crews are cleaning up behind their work areas and ensuring gutters and adjacent streets remain clear of debris.
- A second crew will begin work on Monday, February 9th, to assist with pipe and inlet installation.
- Crews anticipate reaching 11th Street sometime later this week.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.