Weekly Project Updates 1/19/26 - 1/23/26
Hello Stakeholders,
Below are project updates from this week, as well as for the upcoming week (January 19th - 23rd):
- Monday, January 19, is the Martin Luther King Jr. Holiday. City of Loveland offices will be closed in observance of the holiday; however, construction crews will continue working on site.
- The milling crew completed milling on Roosevelt Avenue and 11th Street in preparation for future pipe installation in the coming weeks.
- The pipe crew continued making steady progress installing the elliptical pipe along 10th Street.
- Crews successfully installed a drop manhole and began moving east toward Harrison Street.
- The pipe crew will continue advancing toward Harrison Street this coming week.
- Once pipe installation reaches Harrison Street, crews will return to install inlets along 10th Street between Franklin Avenue and Roosevelt Avenue, and then between Roosevelt Avenue and Harrison Street, before moving work onto Roosevelt Avenue.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Share Weekly Project Updates 1/19/26 - 1/23/26 on Facebook
Share Weekly Project Updates 1/19/26 - 1/23/26 on Twitter
Share Weekly Project Updates 1/19/26 - 1/23/26 on Linkedin
Email Weekly Project Updates 1/19/26 - 1/23/26 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends