Share Project weekly update 07/15/2024 - 07/19/2024 on Facebook
Share Project weekly update 07/15/2024 - 07/19/2024 on Linkedin
Email Project weekly update 07/15/2024 - 07/19/2024 link
Hello Stakeholders!
Here are the project updates for this week (7/15 -7/19).
- The large 54” storm sewer installation continues on 5th Street and is currently at the intersection of Roosevelt Avenue and 5th Street.
- Following the stormsewer, the waterline installation will begin. Concrete repairs and installations will continue along 5th Street.
- Milling on Roosevelt Avenue is complete and stockpiling of pipe materials will be ongoing.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us with any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.
Share Project weekly update 07/08/2024 - 07/12/2024 on Facebook
Share Project weekly update 07/08/2024 - 07/12/2024 on Linkedin
Email Project weekly update 07/08/2024 - 07/12/2024 link
Hello Stakeholders!
Here are the project updates for this week (7/8 -7/12).
- The team will take off July 4-7 and return to work on Monday, July 8.
- Sheridan west of 5th Street will be off temporary water and paving preparations will continue. A bottom mat is planned for Thursday, August 1.
- A large 54-inch storm sewer will continue to be installed going east on 5th Street to Roosevelt Avenue. Waterline installation will follow.
- Milling and storage of pipe along 5th Street to 7th Street on Roosevelt Avenue is planned for Monday.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.
Share Project weekly update 07/01/2024 - 07/03/2024 on Facebook
Share Project weekly update 07/01/2024 - 07/03/2024 on Linkedin
Email Project weekly update 07/01/2024 - 07/03/2024 link
Hello Stakeholders!
Here are the project updates for this week (7/1 -7/3).
- Waterline will continue to be installed on Sheridan Avenue and should conclude mid-week. A large 54-inch storm sewer will follow, going east from Sheridan Avenue to Roosevelt Avenue.
- Potholing activities for utilities will be occurring concurrently, and vac trucks will assist with meter box replacements during the waterline installation.
- Street preparation for paving and concrete replacements will be ongoing on both Sheridan Avenue and W. 5th Street in preparation for paving activities starting in July.
- The team will take off July 4 - 7 and return to work on the 8th Street.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.
Share Project weekly update 06/24/2024 - 06/28/2024 on Facebook
Share Project weekly update 06/24/2024 - 06/28/2024 on Linkedin
Email Project weekly update 06/24/2024 - 06/28/2024 link
Hello Stakeholders!
Here are the project updates starting this week, 6/24:
- Waterline will continue to be installed on Sheridan Ave. and should conclude mid-week. A large 54-inch storm sewer will follow going east from Sheridan Avenue to Roosevelt Avenue.
- Potholing activities for utilities will be occurring concurrently and vac trucks will be assisting with meter box replacements as the waterline installation occurs.
- Street preparation for paving and concrete replacements will be ongoing on both Sheridan Avenue and W. 5th Street in preparation for paving activities starting in July.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.
Share Project weekly update 06/17/2024 - 06/21/2024 on Facebook
Share Project weekly update 06/17/2024 - 06/21/2024 on Linkedin
Email Project weekly update 06/17/2024 - 06/21/2024 link
Hello Stakeholders!
Here are the project updates starting this week, 6/17:
- Street paving preparation work will occur next week between 4th & 5th Streets on Sheridan Avenue. Bottom mat paving is planned for the following week.
- Concrete crews will continue working on handicap ramps and curb and gutter.
- Storm sewer crews on 5th Street, west of Sheridan Avenue will wrap up their work and new 8-inch waterline will be installed.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.
Share Project weekly update 06/10/2024 - 06/14/2024 on Facebook
Share Project weekly update 06/10/2024 - 06/14/2024 on Linkedin
Email Project weekly update 06/10/2024 - 06/14/2024 link
Hello Stakeholders!
Here are the project updates starting this week, 6/10:
- This week the new 8-inch waterline will be tied in at Franklin Avenue & 5th Street and begin installation moving east.
- Concrete crews will be installing the curb and gutter.
- Inlets will also be constructed at Franklin Avenue & 5th Street.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.
Share Project weekly update 06/03/2024 - 06/07/2024 on Facebook
Share Project weekly update 06/03/2024 - 06/07/2024 on Linkedin
Email Project weekly update 06/03/2024 - 06/07/2024 link
Hello Stakeholders!
Here are the project updates starting this week, 6/03:
- Storm sewer installation at Franklin Avenue & 5th Street will continue through the week.
- The waterline will begin following the storm sewer the following week.
- Concrete repairs and ADA-compliant handicap ramps will also be built concurrently on Sheridan Avenue in preparation for paving at the end of June.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.
Share Project weekly update 05/27/2024 - 05/31/2024 on Facebook
Share Project weekly update 05/27/2024 - 05/31/2024 on Linkedin
Email Project weekly update 05/27/2024 - 05/31/2024 link
Hello Stakeholders!
Here are the project updates starting this week, 5/27
- No work was performed on Monday, 5/27, due to the observance of Memorial Day.
- The stormsewer will continue to be installed between Franklin and Sheridan. Upon completion, the stormsewer will begin from Sheridan Avenue to Roosevelt Avenue
- Waterline installation will begin the first week of June following the stormsewer.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.
Share Project weekly update 05/13/2024 - 05/17/2024 on Facebook
Share Project weekly update 05/13/2024 - 05/17/2024 on Linkedin
Email Project weekly update 05/13/2024 - 05/17/2024 link
Hello Stakeholders!
Here are the project updates starting this week, 5/13
- Next week, work will begin installing the 18-inch lateral to the west on 5th Street. This process will be much faster compared to working with the 54-inch pipe.
- The waterline installation will follow the storm sewer installation.
- Concrete repairs and ADA ramp installations will work up Sheridan Avenue from 4th Street to 5th Street.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.
Share Project weekly update 05/06/2024 - 05/10/2024 on Facebook
Share Project weekly update 05/06/2024 - 05/10/2024 on Linkedin
Email Project weekly update 05/06/2024 - 05/10/2024 link
Hello Stakeholders!
Here are the project updates starting this week, 5/6.
- Work will continue installing the large 54-inch storm sewer on Sheridan Avenue.
- Upon reaching 5th Street, a storm sewer lateral will be built west of the Franklin Avenue intersection.
- A new waterline will follow the storm sewer.
- Upon completing the lateral to Franklin Avenue, the large storm sewer trunkline will begin again at 5th Street and Sheridan Avenue and travel east to Roosevelt Avenue.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 5:00 p.m. Please contact us if you have any questions at garfieldharrisonstormdrain@gmail.com or 970-716-5155.
Thank you for your continued patience and support.