Weekly Project Updates 12/22/25 - 12/26/25

Here are the project updates for the week of December 22nd - 26th:

  • We had another week of generally great weather. While two windy days created some challenges, crews were still able to make good progress.
  • The base crew prepared the subgrade and readied the Franklin Avenue and 10th Street intersection for paving.
  • The paving crew placed the bottom lift of asphalt on sections of 10th Street both east and west of Franklin Avenue, as well as within the Franklin and 10th Street intersection.
  • The pipe crew advanced west past Roosevelt Avenue, reaching Manhole 9 and the next two inlets. Crews will continue installing pipe through the Roosevelt Avenue and 10th Street intersection, then return next week to install the remaining two inlets.

Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Share Weekly Project Updates 12/22/25 - 12/26/25 on Facebook Share Weekly Project Updates 12/22/25 - 12/26/25 on Twitter Share Weekly Project Updates 12/22/25 - 12/26/25 on Linkedin Email Weekly Project Updates 12/22/25 - 12/26/25 link
#<Object:0x00007ff80dace718>