Project Updates for 3/9/26 - 3/13/26

Below are project updates from this week, as well as for the upcoming week (March 9th - 13th):

  • The main line crew has moved on to other projects, and the inlet crew is currently working on site. Several inlets were installed this week.
  • The concrete crew is following behind the main crew’s work from last week and the inlet crew’s recent installations.
  • Next week, crews plan to complete the remaining two inlets—one at the northwest corner of Roosevelt Avenue and 10th Street, and the other on 11th Street west of Roosevelt Avenue.
  • The concrete crew will continue working behind the inlet crew and will also replace sections of damaged curb and gutter in areas where drainage does not properly flow to the new inlets.

Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Pictures showing crews installing concrete curb, gutter and stormwater infrastructure.