First Street Wastewater Interceptor Project
To support Loveland’s rapidly growing east side—where new neighborhoods, schools, and businesses are emerging—a major wastewater infrastructure project will begin in late December 2025. This project is part of the City’s broader effort to expand the wastewater system, ensuring it can meet the community’s long-term needs with increased capacity and improved reliability.
Scope of Work
Wastewater System Improvements
Garney Construction will install a new 36-inch wastewater interceptor on First Street from Denver Avenue east to Willow Bend Park. The larger line will relieve pressure on the existing 24-inch pipe and enhance the system’s ability to handle future growth. This work marks the second phase of a planned collection system upgrade that runs from the East Side Lift Station downstream to the Wastewater Reclamation Facility.
A wastewater interceptor is a large underground pipe that carries wastewater to a treatment plant. Acting like a main highway for the sewer system, it collects flow from smaller neighborhood pipes and moves it efficiently down the line. The new line will span about 1,500 feet.
Construction will move from downstream to upstream along First Street, with excavation reaching depths of up to 19 feet. The new line will run parallel to the existing line, boosting both capacity and stability.
Work at the Farmer’s Ditch crossing will begin in early January and continue into February, weather permitting, when the ditch is inactive. At the intersection of First Street and Denver Avenue, deep excavation will require a full closure of First Street from Denver Avenue to Sculptor Drive for about four weeks. Eastbound First Street is scheduled to open in February, while westbound First Street is scheduled to remain closed through May 2026. Detours will be available via U.S. Highway 34 or Mountain Lion Avenue.
Construction Impacts
Traffic & Access
During construction, traffic control measures will be in place to maintain safe travel through the area. Temporary traffic pattern changes should be expected on East 1st Street and, to a lesser degree, North Denver Avenue, but local access to residences and for business deliveries and customers will be maintained.
Schedule
Work will occur along East 1st Street, starting at North Denver Avenue and progressing east. For the most part, work will take place between 7 a.m. and 5 p.m. Monday through Friday. There may be occasional Saturday work.
Pedestrian Safety
For everyone’s safety, temporary construction fencing will be installed around open trenches. Pedestrians are encouraged to use caution and maintain a safe distance from construction activities at all times, both during and after working hours.
Planning and Funding
The City’s 2021 Wastewater Collections System Master Plan identified a capacity limitation in existing infrastructure in the Eastside and New Boyd Basins. This is a high priority improvement project due to anticipated growth in east Loveland.
The Project is funded with 2025 Wastewater Utility budget funds. Garney Construction, a water utilities contractor, has been awarded a construction contract for completion of this work. The total contract amount for this work is $3,166,866.00. The project is anticipated to begin construction in January of 2026 and is expected to be complete by May of 2026.
The planning and launch of this project remain on schedule and under budget.
To support Loveland’s rapidly growing east side—where new neighborhoods, schools, and businesses are emerging—a major wastewater infrastructure project will begin in late December 2025. This project is part of the City’s broader effort to expand the wastewater system, ensuring it can meet the community’s long-term needs with increased capacity and improved reliability.
Scope of Work
Wastewater System Improvements
Garney Construction will install a new 36-inch wastewater interceptor on First Street from Denver Avenue east to Willow Bend Park. The larger line will relieve pressure on the existing 24-inch pipe and enhance the system’s ability to handle future growth. This work marks the second phase of a planned collection system upgrade that runs from the East Side Lift Station downstream to the Wastewater Reclamation Facility.
A wastewater interceptor is a large underground pipe that carries wastewater to a treatment plant. Acting like a main highway for the sewer system, it collects flow from smaller neighborhood pipes and moves it efficiently down the line. The new line will span about 1,500 feet.
Construction will move from downstream to upstream along First Street, with excavation reaching depths of up to 19 feet. The new line will run parallel to the existing line, boosting both capacity and stability.
Work at the Farmer’s Ditch crossing will begin in early January and continue into February, weather permitting, when the ditch is inactive. At the intersection of First Street and Denver Avenue, deep excavation will require a full closure of First Street from Denver Avenue to Sculptor Drive for about four weeks. Eastbound First Street is scheduled to open in February, while westbound First Street is scheduled to remain closed through May 2026. Detours will be available via U.S. Highway 34 or Mountain Lion Avenue.
Construction Impacts
Traffic & Access
During construction, traffic control measures will be in place to maintain safe travel through the area. Temporary traffic pattern changes should be expected on East 1st Street and, to a lesser degree, North Denver Avenue, but local access to residences and for business deliveries and customers will be maintained.
Schedule
Work will occur along East 1st Street, starting at North Denver Avenue and progressing east. For the most part, work will take place between 7 a.m. and 5 p.m. Monday through Friday. There may be occasional Saturday work.
Pedestrian Safety
For everyone’s safety, temporary construction fencing will be installed around open trenches. Pedestrians are encouraged to use caution and maintain a safe distance from construction activities at all times, both during and after working hours.
Planning and Funding
The City’s 2021 Wastewater Collections System Master Plan identified a capacity limitation in existing infrastructure in the Eastside and New Boyd Basins. This is a high priority improvement project due to anticipated growth in east Loveland.
The Project is funded with 2025 Wastewater Utility budget funds. Garney Construction, a water utilities contractor, has been awarded a construction contract for completion of this work. The total contract amount for this work is $3,166,866.00. The project is anticipated to begin construction in January of 2026 and is expected to be complete by May of 2026.
The planning and launch of this project remain on schedule and under budget.
-
Construction Update: April 17
Share Construction Update: April 17 on Facebook Share Construction Update: April 17 on Twitter Share Construction Update: April 17 on Linkedin Email Construction Update: April 17 linkEast First Street Closure Extended Due to Ground Conditions
Construction for the First Street Wastewater Improvements project is ongoing. Due to unexpected ground conditions, the full closure of East First Street, just east of North Denver Avenue, will be extended. Local residents, businesses and emergency vehicles will still have access.
Groundwater and wet soil are making it hard to build a solid base for new pavement. The soil conditions are not ideal, so crews need more time to refill the trench, dry and stabilize the ground, and add structural materials (rock). This makes the work take longer than usual. In the coming weeks, lanes are expected to reopen in phases as work progresses.
Detour Information:
During the closure, traffic will follow these detours:
- Eastbound detour: Eastbound traffic on First Street will be detoured north on Denver Avenue, east on US 34/Eisenhower Boulevard, and south on North Boyd Lake Avenue.
- Westbound detour: Westbound traffic traveling to First Street will be routed east on First Street (which becomes Corvus Drive and then Fifth Street) to North Boyd Lake Avenue, then north to US 34/ Eisenhower Boulevard, west to Denver Avenue, and south back to First Street.
The schedule is subject to change due to weather or other unexpected conditions. For questions about the project, please call 970-783-7225 or email firststreetimprovementsproject@getinfonow.us.
East First Street Closure Extended Due to Ground Conditions
Construction for the First Street Wastewater Improvements project is ongoing. Due to unexpected ground conditions, the full closure of East First Street, just east of North Denver Avenue, will be extended. Local residents, businesses and emergency vehicles will still have access.
Groundwater and wet soil are making it hard to build a solid base for new pavement. The soil conditions are not ideal, so crews need more time to refill the trench, dry and stabilize the ground, and add structural materials (rock). This makes the work take longer than usual. In the coming weeks, lanes are expected to reopen in phases as work progresses.
Detour Information:
During the closure, traffic will follow these detours:
- Eastbound detour: Eastbound traffic on First Street will be detoured north on Denver Avenue, east on US 34/Eisenhower Boulevard, and south on North Boyd Lake Avenue.
- Westbound detour: Westbound traffic traveling to First Street will be routed east on First Street (which becomes Corvus Drive and then Fifth Street) to North Boyd Lake Avenue, then north to US 34/ Eisenhower Boulevard, west to Denver Avenue, and south back to First Street.
The schedule is subject to change due to weather or other unexpected conditions. For questions about the project, please call 970-783-7225 or email firststreetimprovementsproject@getinfonow.us.
-
FOR RELEASE: East First Street Full Closure Extended Through Mid-April
Share FOR RELEASE: East First Street Full Closure Extended Through Mid-April on Facebook Share FOR RELEASE: East First Street Full Closure Extended Through Mid-April on Twitter Share FOR RELEASE: East First Street Full Closure Extended Through Mid-April on Linkedin Email FOR RELEASE: East First Street Full Closure Extended Through Mid-April linkMEDIA RELEASE
CONTACT: Nicole Yost, Director of Communication and Engagement
970-962-2302, nicole.yost@cityofloveland.orgEast First Street Full Closure Extended Through Mid-April
Loveland, Colo. – March 25, 2026 – The City of Loveland will extend the full closure of East First Street, just east of the North Denver Avenue intersection, through mid-April because current conditions do not allow the eastbound lane to safely reopen during wastewater pipeline installation. Access will be maintained for local residents, businesses and emergency vehicles.
Before construction began, the City took steps to identify underground conditions to plan safe travel through the work zone. Despite these efforts, crews have encountered unexpected utility conflicts and varying soil conditions during construction.
Keeping the full closure in place is expected to speed up construction and could allow the road to reopen two to three weeks early, in early May. After the full closure, the eastbound lane will reopen to through traffic, while the westbound lane will remain closed into early May. The project is expected to be completed by June 2026.
Detour information
During the full closure, eastbound traffic on First Street will be detoured north on Denver Avenue, east on U.S. 34/Eisenhower Boulevard and south on Boyd Lake Avenue. As crews move east, they will work to reopen sections of the road for additional local access as soon as it is safe.
Westbound traffic will detour east on First Street, which becomes Corvus Drive and East Fifth Street, to connect with Boyd Lake Avenue. Traffic will then travel north to U.S. 34/Eisenhower Boulevard, west to Denver Avenue and south back to First Street.
The project schedule is subject to change due to weather or other unforeseen conditions.
For more information, please visit letstalkloveland.org/first-street-wastewater-improvements.
MEDIA RELEASE
CONTACT: Nicole Yost, Director of Communication and Engagement
970-962-2302, nicole.yost@cityofloveland.orgEast First Street Full Closure Extended Through Mid-April
Loveland, Colo. – March 25, 2026 – The City of Loveland will extend the full closure of East First Street, just east of the North Denver Avenue intersection, through mid-April because current conditions do not allow the eastbound lane to safely reopen during wastewater pipeline installation. Access will be maintained for local residents, businesses and emergency vehicles.
Before construction began, the City took steps to identify underground conditions to plan safe travel through the work zone. Despite these efforts, crews have encountered unexpected utility conflicts and varying soil conditions during construction.
Keeping the full closure in place is expected to speed up construction and could allow the road to reopen two to three weeks early, in early May. After the full closure, the eastbound lane will reopen to through traffic, while the westbound lane will remain closed into early May. The project is expected to be completed by June 2026.
Detour information
During the full closure, eastbound traffic on First Street will be detoured north on Denver Avenue, east on U.S. 34/Eisenhower Boulevard and south on Boyd Lake Avenue. As crews move east, they will work to reopen sections of the road for additional local access as soon as it is safe.
Westbound traffic will detour east on First Street, which becomes Corvus Drive and East Fifth Street, to connect with Boyd Lake Avenue. Traffic will then travel north to U.S. 34/Eisenhower Boulevard, west to Denver Avenue and south back to First Street.
The project schedule is subject to change due to weather or other unforeseen conditions.
For more information, please visit letstalkloveland.org/first-street-wastewater-improvements.
-
FOR RELEASE: First Street Wastewater Interceptor Project full road closure
Share FOR RELEASE: First Street Wastewater Interceptor Project full road closure on Facebook Share FOR RELEASE: First Street Wastewater Interceptor Project full road closure on Twitter Share FOR RELEASE: First Street Wastewater Interceptor Project full road closure on Linkedin Email FOR RELEASE: First Street Wastewater Interceptor Project full road closure linkMEDIA RELEASE
CONTACT: Nicole Yost, Director of Communication and Engagement
970-962-2302, Nicole.Yost@cityofloveland.orgFirst Street Wastewater Interceptor Project Full Road Closure
LOVELAND, Colo. – February 20, 2026 – The City of Loveland will close both eastbound and westbound East First Street, east of the North Denver Avenue intersection, beginning Monday, Feb. 23, to allow crews to install a wastewater pipeline beneath the roadway. The closure is expected to last approximately four weeks, weather permitting. Access will be maintained for local residents, businesses and emergency vehicles.
During the closure, eastbound traffic on First Street will be detoured north on Denver Avenue, east on US 34/East Eisenhower Boulevard, and south on North Boyd Lake Avenue. Westbound traffic traveling to First Street will be detoured east on First Street, which becomes Corvus Drive and then East Fifth Street, to North Boyd Lake Avenue. Traffic will then travel north to US 34/ Eisenhower Boulevard, west to Denver Avenue, and south back to First Street. Local access will remain for residents and businesses.

Following the full closure, the eastbound lane will reopen to through traffic, with the westbound lane remaining closed through May 2026 as construction continues.
The project schedule is subject to change due to weather or other unforeseen conditions.
For more information, please visit letstalkloveland.org/first-street-wastewater-improvements.
MEDIA RELEASE
CONTACT: Nicole Yost, Director of Communication and Engagement
970-962-2302, Nicole.Yost@cityofloveland.orgFirst Street Wastewater Interceptor Project Full Road Closure
LOVELAND, Colo. – February 20, 2026 – The City of Loveland will close both eastbound and westbound East First Street, east of the North Denver Avenue intersection, beginning Monday, Feb. 23, to allow crews to install a wastewater pipeline beneath the roadway. The closure is expected to last approximately four weeks, weather permitting. Access will be maintained for local residents, businesses and emergency vehicles.
During the closure, eastbound traffic on First Street will be detoured north on Denver Avenue, east on US 34/East Eisenhower Boulevard, and south on North Boyd Lake Avenue. Westbound traffic traveling to First Street will be detoured east on First Street, which becomes Corvus Drive and then East Fifth Street, to North Boyd Lake Avenue. Traffic will then travel north to US 34/ Eisenhower Boulevard, west to Denver Avenue, and south back to First Street. Local access will remain for residents and businesses.

Following the full closure, the eastbound lane will reopen to through traffic, with the westbound lane remaining closed through May 2026 as construction continues.
The project schedule is subject to change due to weather or other unforeseen conditions.
For more information, please visit letstalkloveland.org/first-street-wastewater-improvements.
-
Construction Update: February 13
Share Construction Update: February 13 on Facebook Share Construction Update: February 13 on Twitter Share Construction Update: February 13 on Linkedin Email Construction Update: February 13 linkHello Loveland!
Here are our project updates and a look at upcoming work.
Crews have been busy since work kicked into high gear in mid-January. They have installed erosion controls, removed trees, potholed, drilled dewatering wells to manage groundwater, installed manholes and more recently completed the first phase of bypass pumping. Work now continues with excavating and trenching for installation of the first segments of new pipeline.
Upcoming Work and Traffic Impacts
-
Monday, Feb. 16:Westbound access on East First Avenue will be closed to allow crews to allow construction crews to begin surface preparation and demolition ahead of pipeline construction on First Street. Eastbound traffic and local access will remain open.
- Detour: Westbound traffic traveling to First Street will be detoured east on First Street, which becomes Corvus Drive and then East Fifth Street, to North Boyd Lake Avenue, then north to U.S. 34/East Eisenhower Boulevard, west to Denver Avenue and back south to First Street.
-
Beginning mid- to late February: First Street is expected to be fully closed to both eastbound and westbound traffic to allow construction crews to install a wastewater pipeline beneath the roadway. The closure will remain in place for approximately three to four weeks, weather permitting. Local resident and business access will remain.
- Eastbound detour: Eastbound traffic on First Street will be detoured north on Denver Avenue, east on US 34/Eisenhower Boulevard, and south on North Boyd Lake Avenue.
- Westbound detour: Westbound traffic traveling to First Street will be routed east on First Street (which becomes Corvus Drive and then Fifth Street) to North Boyd Lake Avenue, then north to US 34/ Eisenhower Boulevard, west to Denver Avenue, and south back to First Street.
Working hours
Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 5:00 p.m. with occasional Saturday work needed.
Project schedules are subject to change due to weather or other unforeseen conditions.
To contact the project team, call 970-783-7225 or email firststreetimprovementsproject@getinfonow.us.
Thank you for your patience as we complete these improvements.
Hello Loveland!
Here are our project updates and a look at upcoming work.
Crews have been busy since work kicked into high gear in mid-January. They have installed erosion controls, removed trees, potholed, drilled dewatering wells to manage groundwater, installed manholes and more recently completed the first phase of bypass pumping. Work now continues with excavating and trenching for installation of the first segments of new pipeline.
Upcoming Work and Traffic Impacts
-
Monday, Feb. 16:Westbound access on East First Avenue will be closed to allow crews to allow construction crews to begin surface preparation and demolition ahead of pipeline construction on First Street. Eastbound traffic and local access will remain open.
- Detour: Westbound traffic traveling to First Street will be detoured east on First Street, which becomes Corvus Drive and then East Fifth Street, to North Boyd Lake Avenue, then north to U.S. 34/East Eisenhower Boulevard, west to Denver Avenue and back south to First Street.
-
Beginning mid- to late February: First Street is expected to be fully closed to both eastbound and westbound traffic to allow construction crews to install a wastewater pipeline beneath the roadway. The closure will remain in place for approximately three to four weeks, weather permitting. Local resident and business access will remain.
- Eastbound detour: Eastbound traffic on First Street will be detoured north on Denver Avenue, east on US 34/Eisenhower Boulevard, and south on North Boyd Lake Avenue.
- Westbound detour: Westbound traffic traveling to First Street will be routed east on First Street (which becomes Corvus Drive and then Fifth Street) to North Boyd Lake Avenue, then north to US 34/ Eisenhower Boulevard, west to Denver Avenue, and south back to First Street.
Working hours
Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 5:00 p.m. with occasional Saturday work needed.
Project schedules are subject to change due to weather or other unforeseen conditions.
To contact the project team, call 970-783-7225 or email firststreetimprovementsproject@getinfonow.us.
Thank you for your patience as we complete these improvements.
-
Monday, Feb. 16:Westbound access on East First Avenue will be closed to allow crews to allow construction crews to begin surface preparation and demolition ahead of pipeline construction on First Street. Eastbound traffic and local access will remain open.
-
FOR RELEASE: First Street Wastewater Interceptor Project westbound closure
Share FOR RELEASE: First Street Wastewater Interceptor Project westbound closure on Facebook Share FOR RELEASE: First Street Wastewater Interceptor Project westbound closure on Twitter Share FOR RELEASE: First Street Wastewater Interceptor Project westbound closure on Linkedin Email FOR RELEASE: First Street Wastewater Interceptor Project westbound closure linkFOR IMMEDIATE RELEASE
First Street Wastewater Interceptor Project westbound closure
LOVELAND, Colo. – February 13, 2026 – The City of Loveland will close westbound East First Street east of the Denver Avenue intersection beginning Monday, Feb. 16 to allow construction crews to begin surface preparation and demolition ahead of pipeline construction on First Street. Access will be maintained for local residents, businesses and emergency vehicles.
A posted detour will be in place during the closure. Westbound motorists traveling to First Street will be routed east on First Street, which becomes Corvus Drive and then East Fifth Street, to North Boyd Lake Avenue, then north to U.S. 34/East Eisenhower Boulevard, west to Denver Avenue and back south to First Street. Local access will remain for residents and businesses.

Beginning in late February, First Street is expected to be fully closed to eastbound and westbound traffic for approximately four weeks with local access maintained for residents, businesses, and emergency vehicles. Following the full closure, the eastbound lane will reopen to through traffic, with the westbound lane remaining closed through May 2026 as construction continues.
The project schedule is subject to change due to weather or other unforeseen conditions.
For more information, please visit letstalkloveland.org/first-street-wastewater-improvements.
CONTACT: Nicole Yost, Director of Communication and Engagement
970-962-2302, Nicole.Yost@cityofloveland.orgFOR IMMEDIATE RELEASE
First Street Wastewater Interceptor Project westbound closure
LOVELAND, Colo. – February 13, 2026 – The City of Loveland will close westbound East First Street east of the Denver Avenue intersection beginning Monday, Feb. 16 to allow construction crews to begin surface preparation and demolition ahead of pipeline construction on First Street. Access will be maintained for local residents, businesses and emergency vehicles.
A posted detour will be in place during the closure. Westbound motorists traveling to First Street will be routed east on First Street, which becomes Corvus Drive and then East Fifth Street, to North Boyd Lake Avenue, then north to U.S. 34/East Eisenhower Boulevard, west to Denver Avenue and back south to First Street. Local access will remain for residents and businesses.

Beginning in late February, First Street is expected to be fully closed to eastbound and westbound traffic for approximately four weeks with local access maintained for residents, businesses, and emergency vehicles. Following the full closure, the eastbound lane will reopen to through traffic, with the westbound lane remaining closed through May 2026 as construction continues.
The project schedule is subject to change due to weather or other unforeseen conditions.
For more information, please visit letstalkloveland.org/first-street-wastewater-improvements.
CONTACT: Nicole Yost, Director of Communication and Engagement
970-962-2302, Nicole.Yost@cityofloveland.org -
FOR RELEASE: First Street Wastewater Interceptor Project Road Closure Saturday, Jan. 24
Share FOR RELEASE: First Street Wastewater Interceptor Project Road Closure Saturday, Jan. 24 on Facebook Share FOR RELEASE: First Street Wastewater Interceptor Project Road Closure Saturday, Jan. 24 on Twitter Share FOR RELEASE: First Street Wastewater Interceptor Project Road Closure Saturday, Jan. 24 on Linkedin Email FOR RELEASE: First Street Wastewater Interceptor Project Road Closure Saturday, Jan. 24 linkCity of Loveland, Colorado
MEDIA RELEASE
CONTACT: Tracey Hewson, Public Information Officer
970-962-3710
tracey.hewson @cityofloveland.orgFirst Street Wastewater Interceptor Project Road Closure Saturday, Jan. 24
LOVELAND, Colo. – January 22, 2026 – The City of Loveland will close a portion of East First Street east of the Denver Avenue intersection from 7 a.m. to 4 p.m. Saturday, Jan. 24, to safely position a crane for tree removal. A posted detour will be in place.
East First Street will be fully closed east of the Denver Avenue intersection during the closure. Eastbound traffic on East First Street will be detoured north on Denver Avenue, east on U.S. 34/East Eisenhower Boulevard and south on North Boyd Lake Avenue. Westbound traffic traveling to East First Street will be detoured east on East First Street, which becomes Corvus Drive and then East Fifth Street, to North Boyd Lake Avenue, then north to U.S. 34/East Eisenhower Boulevard, west to Denver Avenue and back south to East First Street.
The project began in late December. Crews have completed dewatering, the process of removing groundwater from the site to allow deep trench construction. The construction team is scheduled to begin installing new pipe the week of Jan. 26. Beginning in late February, East First Street is expected to be fully closed for three to four weeks to install pipe beneath the roadway. Additional details will be shared as they become available.
Additional project details can be found at https://www.letstalkloveland.org/first-street-wastewater-improvements. For questions regarding the project, please email tracey.hewson@cityofloveland.org, or call 970-962-3710.

City of Loveland, Colorado
MEDIA RELEASE
CONTACT: Tracey Hewson, Public Information Officer
970-962-3710
tracey.hewson @cityofloveland.orgFirst Street Wastewater Interceptor Project Road Closure Saturday, Jan. 24
LOVELAND, Colo. – January 22, 2026 – The City of Loveland will close a portion of East First Street east of the Denver Avenue intersection from 7 a.m. to 4 p.m. Saturday, Jan. 24, to safely position a crane for tree removal. A posted detour will be in place.
East First Street will be fully closed east of the Denver Avenue intersection during the closure. Eastbound traffic on East First Street will be detoured north on Denver Avenue, east on U.S. 34/East Eisenhower Boulevard and south on North Boyd Lake Avenue. Westbound traffic traveling to East First Street will be detoured east on East First Street, which becomes Corvus Drive and then East Fifth Street, to North Boyd Lake Avenue, then north to U.S. 34/East Eisenhower Boulevard, west to Denver Avenue and back south to East First Street.
The project began in late December. Crews have completed dewatering, the process of removing groundwater from the site to allow deep trench construction. The construction team is scheduled to begin installing new pipe the week of Jan. 26. Beginning in late February, East First Street is expected to be fully closed for three to four weeks to install pipe beneath the roadway. Additional details will be shared as they become available.
Additional project details can be found at https://www.letstalkloveland.org/first-street-wastewater-improvements. For questions regarding the project, please email tracey.hewson@cityofloveland.org, or call 970-962-3710.

-
FOR RELEASE: First Street Wastewater Interceptor Project Begins
Share FOR RELEASE: First Street Wastewater Interceptor Project Begins on Facebook Share FOR RELEASE: First Street Wastewater Interceptor Project Begins on Twitter Share FOR RELEASE: First Street Wastewater Interceptor Project Begins on Linkedin Email FOR RELEASE: First Street Wastewater Interceptor Project Begins linkCity of Loveland, Colorado
MEDIA RELEASE
CONTACT: Tracey Hewson, Public Information Officer
970-962-3710
Tracey.Hewson@cityofloveland.orgFirst Street Wastewater Interceptor Project Begins
LOVELAND, Colo - December 9, 2025 - A major wastewater project is set to begin in later this month to support Loveland’s rapidly growing east side, where new neighborhoods, schools and businesses are continuing to take shape. Early work will focus on preparing the site, including establishing staging areas, installing erosion controls, removing select trees and conducting utility potholing and drilling. Equipment staging will take place outside the right-of-way south of the E. First Street and North Denver Avenue intersection, as well as at the northeast corner of Willow Bend Park. No lane closures will impact traffic during this stage of work.
To meet the community’s long-term needs, the city is expanding its wastewater system to increase capacity and improve reliability. Garney Construction will install a new 36-inch wastewater interceptor from Denver Avenue east to Willow Bend Park. The larger line will provide additional capacity within the basin and enhance the system’s ability to handle future growth. This work marks the second phase of a planned collection system upgrade that runs from the East Side Lift Station downstream to the Wastewater Reclamation Facility.
A wastewater interceptor is a large underground pipe that carries wastewater to a treatment plant. Acting like a main highway for the sewer system, it collects flow from smaller neighborhood pipes and moves it efficiently down the line. The new line will span about 1,500 feet.
Construction will move from downstream to upstream, with excavation reaching depths of up to 19 feet. The new line will run parallel to the existing line, boosting both capacity and stability.
Work at the Farmer’s Ditch crossing will begin in mid-January and will continue into February, when the ditch is inactive. At the intersection of First Street and Denver Avenue, deep excavation will require a full closure of First Street from Denver Avenue to Sculptor Drive for about four weeks. Eastbound First Street is scheduled to open in February, while westbound First Street is scheduled to remain closed through May 2026. Detours will be available via U.S. Highway 34 or Mountain Lion Avenue.
The project remains on schedule and under budget.
For more information, please visit https://www.letstalkloveland.org.
City of Loveland, Colorado
MEDIA RELEASE
CONTACT: Tracey Hewson, Public Information Officer
970-962-3710
Tracey.Hewson@cityofloveland.orgFirst Street Wastewater Interceptor Project Begins
LOVELAND, Colo - December 9, 2025 - A major wastewater project is set to begin in later this month to support Loveland’s rapidly growing east side, where new neighborhoods, schools and businesses are continuing to take shape. Early work will focus on preparing the site, including establishing staging areas, installing erosion controls, removing select trees and conducting utility potholing and drilling. Equipment staging will take place outside the right-of-way south of the E. First Street and North Denver Avenue intersection, as well as at the northeast corner of Willow Bend Park. No lane closures will impact traffic during this stage of work.
To meet the community’s long-term needs, the city is expanding its wastewater system to increase capacity and improve reliability. Garney Construction will install a new 36-inch wastewater interceptor from Denver Avenue east to Willow Bend Park. The larger line will provide additional capacity within the basin and enhance the system’s ability to handle future growth. This work marks the second phase of a planned collection system upgrade that runs from the East Side Lift Station downstream to the Wastewater Reclamation Facility.
A wastewater interceptor is a large underground pipe that carries wastewater to a treatment plant. Acting like a main highway for the sewer system, it collects flow from smaller neighborhood pipes and moves it efficiently down the line. The new line will span about 1,500 feet.
Construction will move from downstream to upstream, with excavation reaching depths of up to 19 feet. The new line will run parallel to the existing line, boosting both capacity and stability.
Work at the Farmer’s Ditch crossing will begin in mid-January and will continue into February, when the ditch is inactive. At the intersection of First Street and Denver Avenue, deep excavation will require a full closure of First Street from Denver Avenue to Sculptor Drive for about four weeks. Eastbound First Street is scheduled to open in February, while westbound First Street is scheduled to remain closed through May 2026. Detours will be available via U.S. Highway 34 or Mountain Lion Avenue.
The project remains on schedule and under budget.
For more information, please visit https://www.letstalkloveland.org.
Follow Project
Videos
-
Click here to play video East 1st Street Wastewater Interceptor Project Join Loveland’s project manager for the East First Street Wastewater Interceptor Project as they introduce an important infrastructure improvement along First Street between Denver Avenue and Willow Bend Park. This work will install a new wastewater collection pipe to increase capacity for growth on the city’s east side and maintain systemwide reliability. The video covers timeline for construction, anticipated traffic impacts and why the project is happening now. These improvements reflect the City’s commitment to reliable infrastructure and a resilient future for Loveland.
Key Dates
-
December 08 2025
-
December 15 2025
-
January 2026
-
February 16 → February 23 2026
-
February → May 2026
Who's Listening
-
Project Communications & PIO
PTPhone 970-783-7225 Email firststreetimprovementsproject@getinfonow.us -
Phone 970-962-3702 Email Donald.Cecil@cityofloveland.org -
Phone 970-962-3521 Email John.Faulkner@cityofloveland.org



