Weekly project updates 9/8/2025 - 9/12/2025

Hello, Loveland!

Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (September 8 – September 12):

  • Madison has been milled from 37th Street to Seven Lakes Drive.
  • Median cover material has been completed.
  • Waterline updates are continuing north on Madison Avenue.
  • Sidewalk continues to be poured around the roundabout.
  • Final grading continues for stabilization.

Looking ahead:

  • Top lift of asphalt on the west, north, and east legs of the roundabout
  • Roadway grading along the milled section on Madison Avenue
  • Waterline updates will continue north on Madison Avenue.
  • Sidewalk will continue to be poured around the roundabout.
  • Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Dr.

Please refer to the photos below for a visual update of progress.

Light poles are installed around the roundabout.

Cassions are installed at the southwest corner of the roundabout.