Weekly project updates 9/22/2025 - 9/26/2025
Hello, Loveland!
Here’s last week's update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned this week (September 29 – October 3):
- Roundabout has been opened to the public
- Stabilization for erosion control applied to banks
- Excavation and asphalt removals continued on Madison
- Waterline work continued near Seven Lakes
Looking ahead:
- Subgrade preparation and fill
- Traffic signal updates on 29th and Madison Avenue
- Waterline updates will continue northward
- Waterline updates near Seven Lakes
- Installation of waterline board insulation
Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
Share Weekly project updates 9/22/2025 - 9/26/2025 on Facebook
Share Weekly project updates 9/22/2025 - 9/26/2025 on Twitter
Share Weekly project updates 9/22/2025 - 9/26/2025 on Linkedin
Email Weekly project updates 9/22/2025 - 9/26/2025 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends