Here’s last week's update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned this week (September 29 – October 3):

  • Roundabout has been opened to the public
  • Stabilization for erosion control applied to banks
  • Excavation and asphalt removals continued on Madison
  • Waterline work continued near Seven Lakes

Looking ahead:

  • Subgrade preparation and fill
  • Traffic signal updates on 29th and Madison Avenue
  • Waterline updates will continue northward
  • Waterline updates near Seven Lakes
  • Installation of waterline board insulation

Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!