Here’s last week's update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned this week (September 29 – October 3):

  • Roundabout has been opened to the public
  • Stabilization for erosion control applied to banks
  • Excavation and asphalt removals continued on Madison
  • Waterline work continued near Seven Lakes

Looking ahead:

  • Subgrade preparation and fill
  • Traffic signal updates on 29th and Madison Avenue
  • Waterline updates will continue northward
  • Waterline updates near Seven Lakes
  • Installation of waterline board insulation

Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!

Share Weekly project updates 9/22/2025 - 9/26/2025 on Facebook Share Weekly project updates 9/22/2025 - 9/26/2025 on Twitter Share Weekly project updates 9/22/2025 - 9/26/2025 on Linkedin Email Weekly project updates 9/22/2025 - 9/26/2025 link

As of April 30, 2026, construction of this project is complete! Thank you for your patience during these critical upgrades. Read the news about the completion.

For questions, contact the Public Works Department at 970-962-2524 or email: PublicWorksInfo@cityofloveland.org. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>