Weekly project updates 9/1/2025 - 9/5/2025

Hello, Loveland!

Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (September 8 – September 12):

  • Madison has been milled from 37th Street to Seven Lakes Drive
  • Median cover material has been completed.
  • Waterline updates are continuing northward.
  • Sidewalk continues to be poured around the roundabout.
  • Final grading continues for stabilization.

Looking ahead:

  • Top lift of asphalt on the west, north, and east fingers of the roundabout
  • Roadway grading along the milled section on Madison Avenue
  • Waterline updates will continue north on Madison Avenue.
  • Sidewalk will continue to be poured around the roundabout.
  • Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Dr.

Please refer to the photos below for a visual update of progress.

Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!

Share Weekly project updates 9/1/2025 - 9/5/2025 on Facebook Share Weekly project updates 9/1/2025 - 9/5/2025 on Twitter Share Weekly project updates 9/1/2025 - 9/5/2025 on Linkedin Email Weekly project updates 9/1/2025 - 9/5/2025 link
#<Object:0x0000000049b5f5d8>