Weekly project updates 9/1/2025 - 9/5/2025
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (September 8 – September 12):
- Madison has been milled from 37th Street to Seven Lakes Drive
- Median cover material has been completed.
- Waterline updates are continuing northward.
- Sidewalk continues to be poured around the roundabout.
- Final grading continues for stabilization.
Looking ahead:
- Top lift of asphalt on the west, north, and east fingers of the roundabout
- Roadway grading along the milled section on Madison Avenue
- Waterline updates will continue north on Madison Avenue.
- Sidewalk will continue to be poured around the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Dr.
Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
As of April 30, 2026, construction of this project is complete! Thank you for your patience during these critical upgrades. Read the news about the completion.
For questions, contact the Public Works Department at 970-962-2524 or email: PublicWorksInfo@cityofloveland.org.