Weekly project updates 8/4/2025 – 8/8/2025

Hello, Loveland!

Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (August 11 – August 15):

  • Finished installing road base in the roundabout.
  • Poured curb & gutter on the outside edges of the roundabout.
  • Set stringline for more curb & gutter (median islands) in the roundabout.
  • Removed part of the old Madison roadway and installed 350-ft of new waterline.

Looking ahead:

  • Pour curb & gutter in the roundabout.
  • Finish waterline installation and testing near Hem Fir. Notifications about water shutoffs will be communicated to affected residents by Loveland Utilities.
  • Start removals of existing signs south of the roundabout.
  • Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Dr.

Please refer to the photos below for a visual update of progress.




Share Weekly project updates 8/4/2025 – 8/8/2025 on Facebook Share Weekly project updates 8/4/2025 – 8/8/2025 on Twitter Share Weekly project updates 8/4/2025 – 8/8/2025 on Linkedin Email Weekly project updates 8/4/2025 – 8/8/2025 link
#<Object:0x000000004a4ef878>