Weekly project updates 8/4/2025 – 8/8/2025
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (August 11 – August 15):
- Finished installing road base in the roundabout.
- Poured curb & gutter on the outside edges of the roundabout.
- Set stringline for more curb & gutter (median islands) in the roundabout.
- Removed part of the old Madison roadway and installed 350-ft of new waterline.
Looking ahead:
- Pour curb & gutter in the roundabout.
- Finish waterline installation and testing near Hem Fir. Notifications about water shutoffs will be communicated to affected residents by Loveland Utilities.
- Start removals of existing signs south of the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Dr.
Please refer to the photos below for a visual update of progress.
Share Weekly project updates 8/4/2025 – 8/8/2025 on Facebook
Share Weekly project updates 8/4/2025 – 8/8/2025 on Twitter
Share Weekly project updates 8/4/2025 – 8/8/2025 on Linkedin
Email Weekly project updates 8/4/2025 – 8/8/2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends