Weekly project updates 8/4/2025 – 8/8/2025
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (August 11 – August 15):
- Finished installing road base in the roundabout.
- Poured curb & gutter on the outside edges of the roundabout.
- Set stringline for more curb & gutter (median islands) in the roundabout.
- Removed part of the old Madison roadway and installed 350-ft of new waterline.
Looking ahead:
- Pour curb & gutter in the roundabout.
- Finish waterline installation and testing near Hem Fir. Notifications about water shutoffs will be communicated to affected residents by Loveland Utilities.
- Start removals of existing signs south of the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Dr.
Please refer to the photos below for a visual update of progress.
Share Weekly project updates 8/4/2025 – 8/8/2025 on Facebook
Share Weekly project updates 8/4/2025 – 8/8/2025 on Twitter
Share Weekly project updates 8/4/2025 – 8/8/2025 on Linkedin
Email Weekly project updates 8/4/2025 – 8/8/2025 link
As of April 30, 2026, construction of this project is complete! Thank you for your patience during these critical upgrades. Read the news about the completion.
For questions, contact the Public Works Department at 970-962-2524 or email: PublicWorksInfo@cityofloveland.org.