Weekly project updates 8/25/2025 - 8/29/2025

Hello, Loveland!

Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (August 25 – August 29):

  • Median cover material has continued.
  • Waterline updates continue along the project.
  • The truck apron has been completed.
  • The concrete pavement for the roundabout has been poured.
  • Grading continues for sidewalk sections.
  • Sleeper slabs have been poured for the roundabout.
  • Asphalt has begun being paved around the roundabout.

Looking ahead:

  • Median cover material will be finished.
  • Waterline updates will continue northward from Hem Fir.
  • Sidewalk will continue to be poured around the roundabout.
  • Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Drive.

Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!

Share Weekly project updates 8/25/2025 - 8/29/2025 on Facebook Share Weekly project updates 8/25/2025 - 8/29/2025 on Twitter Share Weekly project updates 8/25/2025 - 8/29/2025 on Linkedin Email Weekly project updates 8/25/2025 - 8/29/2025 link
#<Object:0x0000000044e43a10>