Weekly project updates 8/25/2025 - 8/29/2025
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (August 25 – August 29):
- Median cover material has continued.
- Waterline updates continue along the project.
- The truck apron has been completed.
- The concrete pavement for the roundabout has been poured.
- Grading continues for sidewalk sections.
- Sleeper slabs have been poured for the roundabout.
- Asphalt has begun being paved around the roundabout.
Looking ahead:
- Median cover material will be finished.
- Waterline updates will continue northward from Hem Fir.
- Sidewalk will continue to be poured around the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Drive.
Please refer to the photos below for a visual update of progress.


Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
As of April 30, 2026, construction of this project is complete! Thank you for your patience during these critical upgrades. Read the news about the completion.
For questions, contact the Public Works Department at 970-962-2524 or email: PublicWorksInfo@cityofloveland.org.