Weekly project updates 8/18/2025 - 8/25/2025

Hello, Loveland!

Here’s last week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (August 18 – August 25):

  • The median cover material is now being poured.
  • The waterline updates are continuing northward of Hem Fir.
  • The construction of the sidewalk continues to be poured around the roundabout.
  • Grading continues for sidewalk sections.

Looking ahead:

  • The median cover material will continue to be poured.
  • The concrete truck apron will be poured in the roundabout.
  • Waterline updates will continue northward from Hem Fir.
  • Sidewalk construction will continue around the roundabout.
  • Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Drive.

Please refer to the photos below for a visual update of progress.

Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link)(External link)(External link)(External link)(External link). Thank you for your patience as we complete these improvements!

Share Weekly project updates 8/18/2025 - 8/25/2025 on Facebook Share Weekly project updates 8/18/2025 - 8/25/2025 on Twitter Share Weekly project updates 8/18/2025 - 8/25/2025 on Linkedin Email Weekly project updates 8/18/2025 - 8/25/2025 link