Weekly project updates 8/11/2025 - 8/15/2025

Hello, Loveland!

Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week:

  • Curb and gutter was poured in the roundabout.
  • Waterline installation and testing are being finalized.
  • Sidewalk is beginning to be poured around the roundabout.
  • Grading continues for sidewalk sections.
  • Roundabout medians are being prepped for median cover material.

Looking ahead:

  • Median cover material will start pouring.
  • Waterline updates will continue northward from Hem Fir.
  • Sidewalk will continue to be poured around the roundabout.
  • Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Drive.

Please refer to the photos below for a visual update of progress.

Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link)(External link)(External link)(External link). Thank you for your patience as we complete these improvements!

Share Weekly project updates 8/11/2025 - 8/15/2025 on Facebook Share Weekly project updates 8/11/2025 - 8/15/2025 on Twitter Share Weekly project updates 8/11/2025 - 8/15/2025 on Linkedin Email Weekly project updates 8/11/2025 - 8/15/2025 link
#<Object:0x0000000048f3cf30>