Weekly project updates 8/11/2025 - 8/15/2025
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week:
- Curb and gutter was poured in the roundabout.
- Waterline installation and testing are being finalized.
- Sidewalk is beginning to be poured around the roundabout.
- Grading continues for sidewalk sections.
- Roundabout medians are being prepped for median cover material.
Looking ahead:
- Median cover material will start pouring.
- Waterline updates will continue northward from Hem Fir.
- Sidewalk will continue to be poured around the roundabout.
- Power, Pulse, and Comcast utility relocations continue south of Seven Lakes Drive.
Please refer to the photos below for a visual update of progress.
Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link)(External link)(External link)(External link). Thank you for your patience as we complete these improvements!
Share Weekly project updates 8/11/2025 - 8/15/2025 on Facebook
Share Weekly project updates 8/11/2025 - 8/15/2025 on Twitter
Share Weekly project updates 8/11/2025 - 8/15/2025 on Linkedin
Email Weekly project updates 8/11/2025 - 8/15/2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends