Weekly project updates 7/7/2025 - 7/11/2025

Hello, Loveland!

  • We successfully closed Madison Avenue from 29th Street to 37th Street, as well as 37th Street from Monroe Avenue to Seven Lakes Drive. Detours and signage have been placed to guide traffic around the construction area.
  • Work began immediately on the new roundabout, starting with removals and erosion control along the project perimeter. Crews removed all asphalt pavement, concrete islands, curb and gutter, signage, and topsoil at the Madison Avenue and 37th Street intersection.
  • Grading work for the new roundabout is now underway. This phase takes longer than removals due to the precision required—especially early on—to establish the correct elevations and build a solid foundation for the new roadway.
  • In the coming days, the project will continue with grading, installation of new drainage pipelines, and utility infrastructure improvements.

Looking ahead:

  • Utility relocations will begin Monday, July 14, starting at the intersection and progressing south to 29th Street.

  • While utility work may not be highly visible from the street, Madison Avenue will continue to take shape and resemble the construction photos below.

  • The Utilities Water Division will also complete lead and copper pipe verifications for properties with direct access along Madison Avenue.

Please refer to the photos below for a visual update of progress.



Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!