Weekly project updates 7/28/2025 - 08/01/2025
Hello, Loveland!
Soft spots in the roundabout area were successfully identified and corrected. While the soil quality wasn't as expected, the project team quickly implemented a solution that ensured a long-term stable foundation. This added some extra time and effort, but the roundabout remains on track to open by October 2025.
Most of the road base has now been installed in the roundabout, bringing us one step closer to paving.
Looking ahead:
Complete the final section of road base inside the roundabout.
Begin forming and pouring the curbs and gutters around the roundabout.
Starting Monday, August 4, crews will begin removing the asphalt from Madison Avenue between Hem Fir and the new roundabout. Adjacent property owners whose access is only available on Madison Avenue have been notified.
Installation of 450 feet of new waterline just north of Hem Fir will begin. Once installed and tested, this line will be connected to the system, allowing the old waterline to be safely abandoned. Any necessary water shutoffs will be communicated in advance by Loveland Utilities.
Utility relocation work for Power, Pulse, and Comcast continues south of Seven Lakes Drive.
Please refer to the photos below for a visual update of progress.

Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link)(External link)(External link). Thank you for your patience as we complete these improvements!