Weekly project updates 7/21/2025 - 7/25/2025
Hello, Loveland!
- Grading work continues for the new roundabout, with crews addressing soft spots caused by recent rain. As a result, some planned activities have been delayed by a few days.
- Storm sewer and irrigation pipe installation in the roundabout area is now complete, and tree removals have begun throughout the entire project area.
Looking ahead:
Utility relocations will continue south of the roundabout toward 29th Street.
Traffic communications conduit will be installed within the roundabout area.
Crews will begin placing new road base in preparation for concrete curb and gutter installation.
Pavement removal on Madison Avenue, between 29th Street and Seven Lakes Drive, will be scheduled soon. Adjacent property owners with access only from Madison Avenue will be notified in advance of this work. The project team will maintain access for all adjacent property owners.
Please refer to the photos below for a visual update of progress.
Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link)(External link). Thank you for your patience as we complete these improvements!