Weekly project updates 11/10/2025 - 11/14/2025
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (November 17 – November 21):
- Cement treatment of the subgrade on Madison Avenue has been completed
- The base was laid for curb and gutter
Looking ahead:
- Base will be laid for Madison Avenue's roadway
- Stringline of concrete will be completed
- Concrete curb and gutter will be poured by the equipment
- Concrete hand form and pour will be completed in some areas
Please refer to the photos below for a visual update of progress.
Cement subgrade application on Madison Avenue
Cement compaction on Madison AvenueWeather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
Share Weekly project updates 11/10/2025 - 11/14/2025 on Facebook
Share Weekly project updates 11/10/2025 - 11/14/2025 on Twitter
Share Weekly project updates 11/10/2025 - 11/14/2025 on Linkedin
Email Weekly project updates 11/10/2025 - 11/14/2025 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends