Weekly project updates 11/10/2025 - 11/14/2025

Hello, Loveland!

Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (November 17 – November 21):

  • Cement treatment of the subgrade on Madison Avenue has been completed
  • The base was laid for curb and gutter

Looking ahead:

  • Base will be laid for Madison Avenue's roadway
  • Stringline of concrete will be completed
  • Concrete curb and gutter will be poured by the equipment
  • Concrete hand form and pour will be completed in some areas

Please refer to the photos below for a visual update of progress.

Cement subgrade application on Madison Avenue

Cement compaction on Madison Avenue

Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!

Share Weekly project updates 11/10/2025 - 11/14/2025 on Facebook Share Weekly project updates 11/10/2025 - 11/14/2025 on Twitter Share Weekly project updates 11/10/2025 - 11/14/2025 on Linkedin Email Weekly project updates 11/10/2025 - 11/14/2025 link
#<Object:0x00007feb0178fc50>