Weekly project updates 11/10/2025 - 11/14/2025

Hello, Loveland!

Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (November 17 – November 21):

  • Cement treatment of the subgrade on Madison Avenue has been completed
  • The base was laid for curb and gutter

Looking ahead:

  • Base will be laid for Madison Avenue's roadway
  • Stringline of concrete will be completed
  • Concrete curb and gutter will be poured by the equipment
  • Concrete hand form and pour will be completed in some areas

Please refer to the photos below for a visual update of progress.

Cement subgrade application on Madison Avenue

Cement compaction on Madison Avenue

Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!

Share Weekly project updates 11/10/2025 - 11/14/2025 on Facebook Share Weekly project updates 11/10/2025 - 11/14/2025 on Twitter Share Weekly project updates 11/10/2025 - 11/14/2025 on Linkedin Email Weekly project updates 11/10/2025 - 11/14/2025 link

As of April 30, 2026, construction of this project is complete! Thank you for your patience during these critical upgrades. Read the news about the completion.

For questions, contact the Public Works Department at 970-962-2524 or email: PublicWorksInfo@cityofloveland.org. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>