Weekly project updates 10/27/2025 - 10/31/2025

Hello, Loveland!

Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (November 3 – November 7):

  • One stormwater culvert was completed
  • Stormwater inlets were formed and poured
  • Sanitary sewer upgrades were completed

Looking ahead:

  • One final stormwater culvert will be placed
  • Roadway fill and grading will continue On Madison Avenue
  • Asphalt will be removed near 29th Street
  • Concrete will be removed near 29th Street
  • Preparation will continue for cement treatment of subgrade

Please refer to the photos below for a visual update of progress.

Stormwater lid installation placement

Sanitary sewer excavation on Madison Avenue

Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link). Thank you for your patience as we complete these improvements!

Share Weekly project updates 10/27/2025 - 10/31/2025 on Facebook Share Weekly project updates 10/27/2025 - 10/31/2025 on Twitter Share Weekly project updates 10/27/2025 - 10/31/2025 on Linkedin Email Weekly project updates 10/27/2025 - 10/31/2025 link

As of April 30, 2026, construction of this project is complete! Thank you for your patience during these critical upgrades. Read the news about the completion.

For questions, contact the Public Works Department at 970-962-2524 or email: PublicWorksInfo@cityofloveland.org. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>