Weekly project updates 10/27/2025 - 10/31/2025
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (November 3 – November 7):
- One stormwater culvert was completed
- Stormwater inlets were formed and poured
- Sanitary sewer upgrades were completed
Looking ahead:
- One final stormwater culvert will be placed
- Roadway fill and grading will continue On Madison Avenue
- Asphalt will be removed near 29th Street
- Concrete will be removed near 29th Street
- Preparation will continue for cement treatment of subgrade
Please refer to the photos below for a visual update of progress.
Stormwater lid installation placement
Sanitary sewer excavation on Madison Avenue Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link). Thank you for your patience as we complete these improvements!
Share Weekly project updates 10/27/2025 - 10/31/2025 on Facebook
Share Weekly project updates 10/27/2025 - 10/31/2025 on Twitter
Share Weekly project updates 10/27/2025 - 10/31/2025 on Linkedin
Email Weekly project updates 10/27/2025 - 10/31/2025 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends