Weekly project updates 10/27/2025 - 10/31/2025

Hello, Loveland!

Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (November 3 – November 7):

  • One stormwater culvert was completed
  • Stormwater inlets were formed and poured
  • Sanitary sewer upgrades were completed

Looking ahead:

  • One final stormwater culvert will be placed
  • Roadway fill and grading will continue On Madison Avenue
  • Asphalt will be removed near 29th Street
  • Concrete will be removed near 29th Street
  • Preparation will continue for cement treatment of subgrade

Please refer to the photos below for a visual update of progress.

Stormwater lid installation placement

Sanitary sewer excavation on Madison Avenue

Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org(External link). Thank you for your patience as we complete these improvements!

Share Weekly project updates 10/27/2025 - 10/31/2025 on Facebook Share Weekly project updates 10/27/2025 - 10/31/2025 on Twitter Share Weekly project updates 10/27/2025 - 10/31/2025 on Linkedin Email Weekly project updates 10/27/2025 - 10/31/2025 link
#<Object:0x00007f34635937d0>