Weekly project updates 10/20/2025 - 10/24/2025
Hello, Loveland!
Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (October 27 – October 31):
- Stormwater installation has continued up towards Seven Lakes Drive
- Comcast has relocated their lines
- Utility poles have been removed
Looking ahead:
- Stormwater culverts will be placed
- Stormwater inlets will be formed and poured
- Sanitary sewer upgrades will be completed
Please refer to the photos below for a visual update of progress.
Stormwater manhole placement on Madison Avenue
Stormwater inlet tie-in on Madison Avenue Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!
As of April 30, 2026, construction of this project is complete! Thank you for your patience during these critical upgrades. Read the news about the completion.
For questions, contact the Public Works Department at 970-962-2524 or email: PublicWorksInfo@cityofloveland.org.