Weekly project updates 10/13/2025 - 10/17/2025

Hello, Loveland!

Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (October 20 – October 24):

  • Stormwater installation has continued near Hem Fir
  • Power vault at 29th Street and Madison Avenue has been relocated

Looking ahead:

  • Stormwater installation will continue northward
  • Comcast will continue relocating lines
  • Utility poles will begin being removed

Please refer to the photos below for a visual update of progress.

New utility vault being placed on 29th Street and Madison Avenue.

Stormwater infrastructure being installed near Hem Fir on Madison Avenue.

Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!