Weekly project update 10/6/2025 - 10/10/2025

Hello, Loveland!

Here’s this week’s update from the Madison Avenue Corridor Improvement Project, along with a look ahead at what’s planned for next week (October 13 – October 17):

  • Traffic signal updates on 29th Street and Madison Avenue have been completed
  • Waterline updates have been completed
  • Installation of waterline board insulation has been completed
  • Stormwater updates are beginning near Hem Fir
  • Power continued to be relocated
  • Comcast has been relocated under 29th Street

Looking ahead:

  • Stormwater installation will continue near Hem Fir
  • Installation of pedestrian push buttons at 29th Street and Madison Avenue
  • Power vault will be relocated on 29th Street and Madison Avenue
  • Cement treatment may begin on Madison Avenue

Monroe Bridge County Project:

Please refer to the photos below for a visual update of progress.


Stormwater materials off in the distance being prepared for installation.


Waterline installation on Madison Avenue

Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 7:00 p.m. To contact the project team, call 970-962-3669 or email PublicWorksInfo@cityofloveland.org. Thank you for your patience as we complete these improvements!

Share Weekly project update 10/6/2025 - 10/10/2025 on Facebook Share Weekly project update 10/6/2025 - 10/10/2025 on Twitter Share Weekly project update 10/6/2025 - 10/10/2025 on Linkedin Email Weekly project update 10/6/2025 - 10/10/2025 link

As of April 30, 2026, construction of this project is complete! Thank you for your patience during these critical upgrades. Read the news about the completion.

For questions, contact the Public Works Department at 970-962-2524 or email: PublicWorksInfo@cityofloveland.org. 