FOR RELEASE: Madison Avenue Corridor Improvement Project starts construction on July 7

City of Loveland, Colorado

MEDIA RELEASE

CONTACT: Illianna Milldrum, Communication and Engagement Specialist, 970-962-2608, Illianna.Milldrum@cityofloveland.org

Madison Avenue Corridor Improvement Project starts construction on July 7

LOVELAND, Colo. – July 3, 2025 –The City of Loveland will begin the Madison Avenue Corridor Improvement Project on Monday, July 7. The project aims to transform Madison Avenue into a multimodal corridor that enhances connectivity, improves accessibility, and supports Loveland’s long-term multimodal transportation goals. The project is targeted to be completed by December 2025, weather permitting.

The improvements along the corridor include:

  • Buffered bike lanes on Madison Avenue from 29th Street to the newly constructed roundabout.
  • Reconstruction of the Madison Avenue and 37th Street intersection to a roundabout with crosswalks and buffered bike lanes.
  • Construction of sidewalks to the east side of the road between Seven Lakes Drive to 37th Street.
  • Addition of two-way left turn lane along Madison Avenue and left turn lane to Seven Lakes Drive.
  • Relocation of critical utilities for storm, water line, gas line and overhead powerlines.
  • An additional art piece—a dandelion sculpture by Loveland artist Karen Cusolito—will join Loveland’s collection of over 500 public sculptures. The piece has been approved and funded by the Art in Public Places program

To limit public disturbances and costs, the City of Loveland Public Works and Utilities Departments will complete the roadway and utility work at the same time to lessen disruptions.

During the construction, Madison Avenue between 29th Street to 37th Street will be closed, as will 37th Street between Monroe Avenue and Seven Lakes Drive. Local access will be maintained to adjacent properties owners; however, most commuters will use North Boise Avenue, Monroe Avenue, West 29th Street and US 34 to travel around the construction zone. Throughout construction, commuters can expect delays and are encouraged to plan accordingly to allow enough time for their commute. Working hours will be Monday through Friday from 7 a.m. to 7 p.m.

“We’re excited to bring long-awaited improvements to the Madison Avenue corridor that reflect what we've heard from the community — safer walking and biking options, smoother traffic flow, and a thoughtful roundabout design. This project is a direct result of resident feedback we received in 2021 and 2022, and we’re excited to bring these improvements to the City of Loveland,” said Civil Engineer Nicole Hahn.

Additional project details including detour maps, images and other project updates can be found at go.lovgov.org/MadisonAvenue. Residents who wish to sign up for weekly project updates, receive the latest information, or contact the project team can email PublicWorksInfo@cityofloveland.org or call 970-962-3669. For Utility concerns, please call 970-962-3000.

About  

The Madison Avenue Corridor Improvement Project aims to improve safety, mobility, and infrastructure along a vital north-south route between 29th and 37th Streets. As one of the city’s most traveled corridors, Madison Avenue connects neighborhoods, schools, parks, and major arterials, including US 287. This project will modernize the corridor by adding buffered bike lanes, new sidewalks, and a new roundabout at 37th Street—all designed to support safer travel for drivers, pedestrians, and cyclists alike. In addition to improving traffic flow, the project will add a feature of public art by Art in Public Places. Construction is expected to be completed by December 2025.

Project Funding

The Madison Avenue Corridor Improvement Project is funded through a combination of the City of Loveland’s General Fund and Capital Expansion Fees (CEFs). From 2019 to 2024, approximately 20% of the project funding came from the General Fund, while the remaining 80% was provided through CEFs. Appropriations for the project began in 2019, with design services completed in 2021. The construction contract was awarded in May 2025, following a competitive bidding process.

Share FOR RELEASE: Madison Avenue Corridor Improvement Project starts construction on July 7 on Facebook Share FOR RELEASE: Madison Avenue Corridor Improvement Project starts construction on July 7 on Twitter Share FOR RELEASE: Madison Avenue Corridor Improvement Project starts construction on July 7 on Linkedin Email FOR RELEASE: Madison Avenue Corridor Improvement Project starts construction on July 7 link