The Garfield-Harrison Project is a large-scale master planned Stormwater project that began in January 2022. The City of Loveland has contracted with Connell Resources to build the Garfield Harrison Storm Drainage Improvements Project. The four separate phases are expected to occur over the next four years (approximately one phase per year.) The project addresses the multiple drainage problems caused by aging infrastructure in the west part of downtown Loveland. Partnering with the City’s Water and Wastewater divisions, Street Maintenance and Rehabilitation Program, and Stormwater Engineering, the project will include new waterlines, sanitary sewers, street resurfacing, and various concrete repairs that will improve ADA accessibility.
The four-year project is designed to improve the following:
Implementation of the City of Loveland Master Drainage Plan
Replacing and upgrading existing stormwater infrastructure to address existing drainage issues and meet current stormwater standards
Installing 18- to 60-inch diameter storm sewer pipes
Replacing existing waterlines and valves to address aging infrastructure
Replacing pavement including asphalt patching, milling, overlays, or full street reconstruction where project components are installed
Rehabilitating and replacing concrete, as well as adding necessary ADA improvements
Disconnecting stormwater from the Little Barnes Ditch during Phase 4
Providing stormwater quality treatment measures within the stormwater system
The four-phase project is expected to be completed in fall 2026, weather permitting.
Phase 4
Phase 4 construction will include a closure on 8th Street from Duffield Court to Colorado Avenue and on 9th Street between Roosevelt and Franklin Avenues to 9th Street. Work will continue in 2026 with a closure of 10th Street from Ferguson Court to Harrison Avenue and North Roosevelt Avenue to 11th Street and McKinley Court.
During construction, local access, deliveries, and services will always be maintained. Residents will experience construction noise and disruptions near their homes. Traffic control personnel will be onsite to direct residents during this work. Typical working hours will be Monday through Friday from approximately 7 a.m. to 5 p.m. Night and weekend work will be occasional and announced in advance.
Recommended detour routes for Phase 4 (Fall 2025) and Phase 4 (2026):
During Phase 4 (Fall 2025), commuters will use West 10th Street, Garfield Avenue, North Taft Avenue or West 4th Street.
During Phase 4 (2026), commuters will use North Taft Avenue, West 8th Street or Garfield Avenue.
Learn about the phasing of this project
How is this project funded?
Estimated total project cost: $18 million
The project is funded through the Stormwater and Water Enterprise Fund. Enterprise funds are dedicated funds supported by user fees in the monthly utility bill. Similar to a business, user fees fund the operation, maintenance, administration, and capital improvement projects required to provide the service.
Stay Informed
To stay informed about this project, subscribe to our email list in the "Stay Informed" section. For immediate questions or concerns, contact us at: garfieldharrisonstormdrain@gmail.com or 970-716-5155. Please allow us at least 24-48 hours to respond to you. Thank you!
The Garfield-Harrison Project is a large-scale master planned Stormwater project that began in January 2022. The City of Loveland has contracted with Connell Resources to build the Garfield Harrison Storm Drainage Improvements Project. The four separate phases are expected to occur over the next four years (approximately one phase per year.) The project addresses the multiple drainage problems caused by aging infrastructure in the west part of downtown Loveland. Partnering with the City’s Water and Wastewater divisions, Street Maintenance and Rehabilitation Program, and Stormwater Engineering, the project will include new waterlines, sanitary sewers, street resurfacing, and various concrete repairs that will improve ADA accessibility.
The four-year project is designed to improve the following:
Implementation of the City of Loveland Master Drainage Plan
Replacing and upgrading existing stormwater infrastructure to address existing drainage issues and meet current stormwater standards
Installing 18- to 60-inch diameter storm sewer pipes
Replacing existing waterlines and valves to address aging infrastructure
Replacing pavement including asphalt patching, milling, overlays, or full street reconstruction where project components are installed
Rehabilitating and replacing concrete, as well as adding necessary ADA improvements
Disconnecting stormwater from the Little Barnes Ditch during Phase 4
Providing stormwater quality treatment measures within the stormwater system
The four-phase project is expected to be completed in fall 2026, weather permitting.
Phase 4
Phase 4 construction will include a closure on 8th Street from Duffield Court to Colorado Avenue and on 9th Street between Roosevelt and Franklin Avenues to 9th Street. Work will continue in 2026 with a closure of 10th Street from Ferguson Court to Harrison Avenue and North Roosevelt Avenue to 11th Street and McKinley Court.
During construction, local access, deliveries, and services will always be maintained. Residents will experience construction noise and disruptions near their homes. Traffic control personnel will be onsite to direct residents during this work. Typical working hours will be Monday through Friday from approximately 7 a.m. to 5 p.m. Night and weekend work will be occasional and announced in advance.
Recommended detour routes for Phase 4 (Fall 2025) and Phase 4 (2026):
During Phase 4 (Fall 2025), commuters will use West 10th Street, Garfield Avenue, North Taft Avenue or West 4th Street.
During Phase 4 (2026), commuters will use North Taft Avenue, West 8th Street or Garfield Avenue.
Learn about the phasing of this project
How is this project funded?
Estimated total project cost: $18 million
The project is funded through the Stormwater and Water Enterprise Fund. Enterprise funds are dedicated funds supported by user fees in the monthly utility bill. Similar to a business, user fees fund the operation, maintenance, administration, and capital improvement projects required to provide the service.
Stay Informed
To stay informed about this project, subscribe to our email list in the "Stay Informed" section. For immediate questions or concerns, contact us at: garfieldharrisonstormdrain@gmail.com or 970-716-5155. Please allow us at least 24-48 hours to respond to you. Thank you!
Phase 2c will begin April 1, 2024, weather permitting. Phase 2c will include:
Street milling will begin March 25.
A large diameter stormsewer pipe will be installed up to 5th Street and then east to Roosevelt. Excavation for the pipe will be extensive and require a full road closure.
New waterline will be installed on 5th Street between California and Roosevelt Avenues.
Phase 3
Garfield-Harrison Project has finished this stage
August 2024 - August 2025
Phase 4
Garfield-Harrison Project is currently at this stage
August 2025 - Late August 2026
Click here to play video
Find out more about the Garfield/Harrison project with this informative video.
Click here to play video
Drone footage of W. 1st Street taken November 2021 prior to Phase 1 construction. Ongoing videos will be created to show construction progress.
Drone footage of W. 1st Street taken November 2021 prior to Phase 1 construction. Ongoing videos will be created to show construction progress.