Key Dates
April 27 2026
Project Begins
- Traffic control devices are set up.
- Construction materials are delivered to site.
April 27 2026
Morning Drive construction begins (approx. 10 weeks total)
- Morning Drive South: April 27-End of June
- Morning Drive North: April 27-Early July
- Traffic will be open from 22nd Street traveling south once Morning Drive South completes.
- After this section is completed, crews will move to the Skyrock Road and Ponderosa Drive sections.
April 28 2026
Resident Information Session
Tuesday, April 28 | 6 p.m.
Thompson School District R2-J Building
800 S. Taft Avenue
June 2026
Anticipated Juniper Lane construction begins (approx. 9 weeks total)
- Work runs Early June-Early August
- This phase will overlap with other phases, starting when Morning Drive is about halfway finished.