FINAL Construction Update: September 28-October 16

Hello Loveland! This will be our final update for the Namaqua Hills waterline project. Thank you for your continued patience and cooperation throughout this work. Your support has helped make this project a success.

Construction Progress

  • All new waterline has been installed, disinfected and tested, and all customers are now connected to permanent service.
  • All necessary meter pit installations throughout the project have completed.
  • Paving over the project areas has completed with the exception of two required asphalt patches.
  • Concrete work in the Skyrock Road and Ponderosa Drive area has wrapped up.

Upcoming Work

  • Some final landscaping restoration and general cleanup may continue over the next couple of weeks as crews complete finishing touches.
  • Asphalt patchwork will be completed near the end of October on Skyrock Road and near the upper pump station on Ponderosa Drive.
  • Additional information: For future updates related to next year's road overlay project or other future maintenance, please keep a look out for communication from the Namaqua Hills GID #8 Road Board.

Traffic Controls

  • All remaining traffic controls for this project will be lifted at the end of the day on Oct. 16. Normal travel routes will resume at that time.
  • Asphalt work near the end of October may require a short road closure or partial road closure. Crews will maintain access wherever possible.

Thank you again for your partnership as we worked to improve the reliability and performance of your neighborhood’s water system. We appreciate your patience and understanding throughout construction.

Workers wearing safety gear are installing or inspecting water infrastructure inside a dug-out trench. One worker is kneeling beside exposed soil and roots, while a large cylindrical waterline component sits partially buried in the foreground. Construction tools and disturbed earth surround the work area.Final project meter pit installation on Skyrock Road.

A trench box surrounds an excavated area where a blue waterline pipe is installed underground. Valves and fittings are visible at the end of the pipe, along with exposed soil and sand inside the trench. Final section of waterline set for disinfection and testing.
A construction worker wearing safety gear stands on a paved surface near a gravel area, using a tool while dust rises nearby. The scene includes trees, a wooden fence, a portable restroom and construction equipment, with bright sunlight casting long shadows.Landscape restoration efforts at the pump station.

Share FINAL Construction Update: September 28-October 16 on Facebook Share FINAL Construction Update: September 28-October 16 on X (formerly Twitter) Share FINAL Construction Update: September 28-October 16 on Linkedin Email FINAL Construction Update: September 28-October 16 link

Work on this project is complete. Thank you, Loveland! 