Construction Update: May 11-22

Hello Loveland!

Here's the latest update on construction from May 11 to May 22 with a look at upcoming weeks as well.

Construction Progress

  • The pump station shutdown on Morning Drive occurred May 12.
    • Resident participation in reducing water use helped make the shutdown successful.
    • During the shutdown, crews installed a new hydrant and valves to support the temporary pump station connection.
  • Crews, built, tested and installed a temporary connection to the pump station. This line, which came online May 21, will remain in service for about two weeks.
  • Excavation and removal of the existing 6-inch cast iron waterline to the pump station is underway, followed by installation of an 8-inch PVC replacement.

Upcoming Work

  • Replacement of the existing 6-inch cast iron line with 8-inch PVC at the pump station will be completed along with disinfection, testing and final connections.
  • The temporary water system built along the shoulders of Morning Drive will be disinfected, tested and connected to homes south of W. 22nd Street.
  • Waterline replacement on Morning Drive is expected to begin in about two weeks.

Traffic Control

  • Morning Drive will remain closed to through traffic while open excavations are present.
  • Homeowners on Morning Drive may need to use the detour to avoid construction areas, but access to homes will be maintained.
  • Skyrock Road to Juniper Lane will remain the designated detour.

Thank you for your patience as we make these improvements.

Crews work to install the new permanent pump station connection.

A view of newly installed valves and "tee" for a fire hydrant connection.

Share Construction Update: May 11-22 on Facebook Share Construction Update: May 11-22 on Twitter Share Construction Update: May 11-22 on Linkedin Email Construction Update: May 11-22 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>