Construction Update: May 11-22
Hello Loveland!
Here's the latest update on construction from May 11 to May 22 with a look at upcoming weeks as well.
Construction Progress
- The pump station shutdown on Morning Drive occurred May 12.
- Resident participation in reducing water use helped make the shutdown successful.
- During the shutdown, crews installed a new hydrant and valves to support the temporary pump station connection.
- Crews, built, tested and installed a temporary connection to the pump station. This line, which came online May 21, will remain in service for about two weeks.
- Excavation and removal of the existing 6-inch cast iron waterline to the pump station is underway, followed by installation of an 8-inch PVC replacement.
Upcoming Work
- Replacement of the existing 6-inch cast iron line with 8-inch PVC at the pump station will be completed along with disinfection, testing and final connections.
- The temporary water system built along the shoulders of Morning Drive will be disinfected, tested and connected to homes south of W. 22nd Street.
- Waterline replacement on Morning Drive is expected to begin in about two weeks.
Traffic Control
- Morning Drive will remain closed to through traffic while open excavations are present.
- Homeowners on Morning Drive may need to use the detour to avoid construction areas, but access to homes will be maintained.
- Skyrock Road to Juniper Lane will remain the designated detour.
Thank you for your patience as we make these improvements.
Crews work to install the new permanent pump station connection.
A view of newly installed valves and "tee" for a fire hydrant connection.