Construction Progress

  • Phase 3 (Juniper Lane) is complete.
    • Crews installed the new 8-inch PVC waterline and upgraded meter pits.
    • Residents were moved from temporary water to the new line after disinfection and testing.
    • Juniper Lane was paved Aug. 7 and reopened to through traffic Aug. 10.
  • Phase 4 (sections Skyrock Road and Ponderosa Drive) is underway.
    • Sections of Skyrock Road and Ponderosa Drive were milled Aug. 3 and are closed to through traffic.
    • A temporary water system was built for Phase 4.
    • Crews have focused on the section of Skyrock Road from Juniper Lane to the Ponderosa Drive intersection.
      • Homes within the work zone were switched to temporary water, expected to remain in place through Aug. 25.
      • Crews completed installation of the new 8-inch PVC waterline and parallel 4-inch waterline in this section.

Upcoming Work

  • Skyrock Road (Juniper Lane to the Ponderosa Drive intersection)
    • Disinfection and testing of the waterline will begin ahead of switching residents to permanent service next week.
    • Meter pit replacements will continue.
    • Milling and road base work start Aug. 24, with paving planned for Friday, Aug. 28.
  • Ponderosa Drive
    • Waterline installation will begin the week of Aug. 24, moving around the curve and north toward the pump station.
    • Meter pit upgrades will occur as needed.
  • Skyrock Road south of the intersection with Ponderosa Drive
    • Crews will return to complete waterline improvements in this area after work on Ponderosa Drive is finished.

Traffic Control

  • Residents on Ponderosa Drive and Ponderosa Place should use the northern entrance to Skyrock Road, Juniper Lane and Morning Drive to avoid construction.
  • Sections of Skyrock Road and Ponderosa Drive remain closed to through traffic.
  • Xcel Energy contractors continue replacing electric poles, which may cause occasional delays.
  • Landscape work on Juniper Lane is active the week of Aug. 17.

Thank you for your patience as we continue making important improvements to your neighborhood’s water system.

A completed section of paving on Juniper Lane.

Crews install a parallel 4-inch waterline alongside the 8-inch waterline on Skyrock Road.

View inside a removed waterline valve.
Boulders removed during construction at the intersection of Skyrock Road and Ponderosa Drive.




Share Construction Update: August 3-14 on Facebook Share Construction Update: August 3-14 on X (formerly Twitter) Share Construction Update: August 3-14 on Linkedin Email Construction Update: August 3-14 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>