Weekly Update for 4/27/26 - 5/1/26
Below are project updates from this week, as well as for the upcoming week (April 27th - May 1st):
- Installation of the inlets at Douglas Avenue and 10th Street has been completed.
- The concrete crew began curb, gutter, and sidewalk work at Douglas Avenue and 10th Street and will continue this week.
- Crews will continue working at Colorado Avenue and 10th Street under a full roadway closure. Due to numerous existing utilities in the area and the age of the infrastructure work is progressing slowly to install the large storm pipe and manholes.
- This week, crews will continue pouring curb, gutter, inlet tops, and sidewalks. They will also begin the new curb and gutter section along the south side of 10th Street ahead of milling and repaving that portion of roadway.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Share Weekly Update for 4/27/26 - 5/1/26 on Facebook
Share Weekly Update for 4/27/26 - 5/1/26 on Twitter
Share Weekly Update for 4/27/26 - 5/1/26 on Linkedin
Email Weekly Update for 4/27/26 - 5/1/26 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends