Weekly Project Updates 7/28/25 - 8/1/25

Here are the project updates for the week:

  • Crews continue installation of inlets, sidewalks, curb and gutter on Colorado and Franklin Avenues, Birkley Court, and 7th Street.
  • Work continues on the roadway preparation at the intersection of 8th Street and Colorado Avenue as well as the Birkley Court and Colorado intersection, and Franklin Avenue.
  • Crews will begin pipe installation on 8th Street, from Colorado Avenue moving west to Duffield Avenue.
  • Flyers will be mailed to residents on 9th Street and Franklin Avenue (9th Street to 10th Street) for next phase of the project.
  • Crews will begin milling 9th Street the week of August 4th.

Weather permitting, work activities are Monday – Friday, 7:00 am – 5:00 pm.