Here are the project updates for the week (7/21-7/25):

  • Crews will continue to install stormwater pipe on Franklin Avenue from 7th Street to 8th Street, including inlets.
  • New inlets and new curb and gutter tie-ins will occur at Birkley Court and Colorado Avenue as well as at the intersection of 8th Street and Colorado Avenue.
  • Road milling on Colorado Avenue from 7th to 8th Streets will be completed ahead of paving.
  • Crews will also mill west, on 8th Street from Colorado to Duffield Avenues to prep for future pipe work.