Here are the project updates for the week:

1) Crews continue to pour concrete on inlets at the 8th Street and Colorado Avenue intersection.
2) The crew will continue to install pipe on Franklin Avenue from 7th Street to 8th Street.
3) Crews will also install inlets at Birkley Court and Colorado Avenue.

Weather permitting, work activities are Monday – Friday, 7:00 am – 5:00 pm.