Weekly Project Updates 12/8/25 - 12/12/25
Here are the project updates for the week of December 8th - 12th:
- Despite the weather during the week of December 1st, the pipe crew continued installing storm pipe along 10th Street. Working around both overhead utilities and underground services made for tight conditions, but progress continued down the street.
- The concrete crew poured two new sections of sidewalk, curb, and gutter, and prepared another section to be poured beginning early in the week.
- Weather permitting, crews plan to mill 10th Street from Roosevelt Avenue to Harrison Street, and possibly Roosevelt Avenue from 10th to 11th Streets.
Weather permitting, work activities are Monday - Friday, 7:00 am to 5:00 pm.

Share Weekly Project Updates 12/8/25 - 12/12/25 on Facebook
Share Weekly Project Updates 12/8/25 - 12/12/25 on Twitter
Share Weekly Project Updates 12/8/25 - 12/12/25 on Linkedin
Email Weekly Project Updates 12/8/25 - 12/12/25 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends