Weekly Project Updates 12/15/25 - 12/19/25
Hello Stakeholders!
Here are the project updates for this week, December 15th - 19th:
- With the recent warm weather, the concrete crew was able to complete curb and gutter work and a section of sidewalk at the northeast corner of Franklin Avenue and 10th Street.
- The pipe crew continued installing storm pipe along 10th Street. Progress was slower due to overhead lines and existing underground utilities, but crews are now more than halfway between Franklin Avenue and Roosevelt Avenue.
- The pipe crew also cleaned up the radius corners behind the newly placed concrete to reduce tripping hazards.
- With favorable weather expected this week, the base and paving crews will place a bottom lift of asphalt at the Franklin Avenue and 10th Street intersection and along 10th Street to help protect the trenches.
- The pipe crew will continue storm pipe installation on 10th Street and, if progress allows, will reach Roosevelt Avenue and transition from the 36-inch round pipe to the elliptical pipe.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Share Weekly Project Updates 12/15/25 - 12/19/25 on Facebook
Share Weekly Project Updates 12/15/25 - 12/19/25 on Twitter
Share Weekly Project Updates 12/15/25 - 12/19/25 on Linkedin
Email Weekly Project Updates 12/15/25 - 12/19/25 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends