Here are the project updates for the week of November 24th - 28th:
- The pipe crew installed four new inlets at the intersection of Franklin Avenue and 10th Street. Two were challenging due to existing utilities being in the way, but the crew successfully completed all installations.
- The paving crew completed the top lift of asphalt on Franklin Avenue from 9th Street to 10th Street. Traffic control has now been removed from 9th Street.
- The pipe crew began installing the east run of storm pipe from the manhole at Franklin Avenue and 10th Street on Thursday, 11/20. Work paused just short of the sanitary sewer main due to the forecasted rain in the evening. Work resumed on Friday morning, 11/21.
- With Thanksgiving on Thursday, the work week will be short. Pipe crews will continue pipe installation Monday and Tuesday, then focus on street cleanup and safety preparations on Wednesday (half day).
- No work will occur on Thursday (Thanksgiving Day), or on Friday 11/28.

Share Weekly Project Updates 11/24/25 - 11/28/25 on Facebook
Share Weekly Project Updates 11/24/25 - 11/28/25 on Twitter
Share Weekly Project Updates 11/24/25 - 11/28/25 on Linkedin
Email Weekly Project Updates 11/24/25 - 11/28/25 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends